DK RESIDENCY
by DK CONSTRUCTION BUILDER AND LAND DEVELOPER · byculla west, MumbaiAlso near Agripada, Nagpada, Mazgaon
Possession date of DK RESIDENCY: 30 December 2021, moved from 31 December 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900004951. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about DK RESIDENCY?
GharKundli’s full report on DK RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004951
- Status
- Lapsed (registration period ended)
- Builder
- DK CONSTRUCTION BUILDER AND LAND DEVELOPER
- Location
- byculla west, Mumbai · 400008
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 90
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DK RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| D K RESIDENCY | 1% | 23% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DK RESIDENCY every month.
DK RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: D K RESIDENCY (24 floors)
- Land: 390 sq m (about 0.1 acres) · sanctioned built-up 2,987 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DK RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DK RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DK RESIDENCY
What is the possession date of DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DK RESIDENCY in byculla west, Mumbai is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for DK RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DK RESIDENCY's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DK RESIDENCY in byculla west, Mumbai is P51900004951.
Is DK RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY is registered as P51900004951 and its status is "Lapsed (registration period ended)".
What is the construction status of DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on D K RESIDENCY is 23% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DK RESIDENCY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DK RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY is registered on MahaRERA as P51900004951, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DK RESIDENCY's possession date changes?
The latest dates are on DK RESIDENCY's MahaRERA page (P51900004951). GharKundli's Kundli Watch sends a free WhatsApp update on DK RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DK RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY has one building filed: D K RESIDENCY with 24 floors.
How big is the land of DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY stands on 390 sq m of land (about 0.1 acres), with 2,987 sq m of sanctioned built-up area.
Where can I read reviews of DK RESIDENCY?
Google Maps has reviews of DK RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DK RESIDENCY?
DK RESIDENCY by DK CONSTRUCTION BUILDER AND LAND DEVELOPER is in byculla west, Mumbai (pincode 400008), near Agripada, Nagpada, Mazgaon, Maharashtra, and is registered on MahaRERA as P51900004951, per GharKundli's check of MahaRERA records.
How many homes are in DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY has 90 homes in 1 tower registered on MahaRERA.
When was DK RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DK RESIDENCY was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on DK RESIDENCY?
No court cases are listed for DK RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of DK RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DK CONSTRUCTION BUILDER AND LAND DEVELOPER.
Check it yourself on MahaRERA
- How to check the possession date of DK RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects in Mumbai Central (400008) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.