Reliable Commercial Complex

by Shree Balaji Developers · Industrial Estate S.O (Nashik), Nashik

Registered on MahaRERA under P51600052728. Status: Completed. Its completion date has moved from December 2024 to December 2025, 12 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Reliable Commercial Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600052728
Status
Completed
Builder
Shree Balaji Developers
Location
Industrial Estate S.O (Nashik), Nashik · 422007
Project type
Others
Registered on
22 Sep 2023
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
0
Sold or booked
19%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
20

Kundli Watch

Reliable Commercial Complex: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Reliable Commercial Complex

Is Reliable Commercial Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Reliable Commercial Complex is registered as P51600052728 and its status is "Completed".

Where is Reliable Commercial Complex?

Reliable Commercial Complex by Shree Balaji Developers is in Industrial Estate S.O (Nashik), Nashik (pincode 422007), Maharashtra, and is registered on MahaRERA as P51600052728, per GharKundli's check of MahaRERA records.

When is possession of Reliable Commercial Complex due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Reliable Commercial Complex in Industrial Estate S.O (Nashik), Nashik is 30 December 2025 — 12 months later than 31 December 2024, the date given at registration.

Does Reliable Commercial Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Reliable Commercial Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Balaji Developers, which has 20 other projects registered on MahaRERA.

Other projects in pincode 422007

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.