Possession date of Shree Eknath Kunj: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600081051, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shree Eknath Kunj?
How the possession date of Shree Eknath Kunj has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shree Eknath Kunj’s extension records on MahaRERA (P51600081051), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Eknath Kunj
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600081051
- Status
- Registered and active
- Builder
- Shree Eknath Buildmat
- Location
- Sai Shrusti Nagar, Nashik · 422007
- Project type
- Residential / Group Housing
- Registered on
- 27 Nov 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Sold or booked
- 28%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shree Eknath Kunj, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Eknath Kunj | 100% | 80% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Eknath Kunj: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Eknath Kunj every month.
Shree Eknath Kunj: buildings, flats and land, as filed on MahaRERA
- Buildings: Eknath Kunj (9 floors, 36 units)
- Car parking: 20 covered, 8 open
- Land: 938 sq m (about 0.2 acres) · sanctioned built-up 2,973 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Eknath Kunj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Eknath Kunj: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shree Eknath Kunj
What is the possession date of Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Eknath Kunj in Sai Shrusti Nagar, Nashik is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shree Eknath Kunj?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Eknath Kunj's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Eknath Kunj in Sai Shrusti Nagar, Nashik is P51600081051.
Is Shree Eknath Kunj registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj is registered as P51600081051 and its status is "Registered and active".
What is the construction status of Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Eknath Kunj is 80% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Shree Eknath Kunj have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shree Eknath Kunj safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj is registered on MahaRERA as P51600081051, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shree Eknath Kunj's possession date changes?
The latest dates are on Shree Eknath Kunj's MahaRERA page (P51600081051). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Eknath Kunj every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Eknath Kunj have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj has one building filed: Eknath Kunj with 9 floors and 36 units.
How much parking does Shree Eknath Kunj have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered and 8 open car parking spaces for Shree Eknath Kunj.
How big is the land of Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj stands on 938 sq m of land (about 0.2 acres), with 2,973 sq m of sanctioned built-up area.
Where can I read reviews of Shree Eknath Kunj?
Google Maps has reviews of Shree Eknath Kunj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shree Eknath Kunj?
Shree Eknath Kunj by Shree Eknath Buildmat is in Sai Shrusti Nagar, Nashik (pincode 422007), Maharashtra, and is registered on MahaRERA as P51600081051, per GharKundli's check of MahaRERA records.
How many homes are in Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj has 36 homes in 1 tower registered on MahaRERA, and 28% of them are sold or booked.
When was Shree Eknath Kunj registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Eknath Kunj was registered on MahaRERA on 27 November 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on Shree Eknath Kunj?
No court cases are listed for Shree Eknath Kunj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Shree Eknath Kunj?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Eknath Buildmat.
Check it yourself on MahaRERA
- How to check the possession date of Shree Eknath Kunj
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.