Possession date of Feriha Heights: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600055909, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Feriha Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Feriha Heights has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA29052621159)

    Reason the builder gave MahaRERA:
    “The project completion and submission of this request have experienced delays primarily on account of procurement challenges, financial constraints, and certain site-related operational issues. These factors have impacted the overall execut…” Read the full reason“The project completion and submission of this request have experienced delays primarily on account of procurement challenges, financial constraints, and certain site-related operational issues. These factors have impacted the overall execution timeline and resulted in a revised pace of work. However, necessary corrective measures are now being implemented to streamline procurement, strengthen financial planning, and resolve site-level bottlenecks to ensure steady progress of the remaining work. We are now actively focused on accelerating the balance construction activities and coordinating…”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Feriha Heights’s extension records on MahaRERA (P51600055909), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Feriha Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600055909
Status
Registered and active
Builder
Aroma Developers
Location
Wadala, Shiwar, Nashik · 422007
Project type
Others
Registered on
29 Apr 2024
Completion date at registration
March 2026
Latest completion date
July 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
24
Sold or booked
46%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Feriha Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Feriha Heights0%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • Feriha Heights: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Feriha Heights every month.

Feriha Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Feriha Heights (8 floors, 28 units)
  • Land: 530 sq m (about 0.1 acres) · sanctioned built-up 1,658 sq m

The builder’s record and reviews

Aroma Developers (a group of 5 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Feriha Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Feriha Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Feriha Heights

What is the possession date of Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Feriha Heights in Wadala, Shiwar, Nashik is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Feriha Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Feriha Heights's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Feriha Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project completion and submission of this request have experienced delays primarily on account of procurement challenges, financial constraints, and certain site-related operational issues. These factors have impacted the overall execution timeline and resulted in a revised pace of work. However, necessary corrective measures are now being implemented to streamline procurement, strengthen financial planning, and resolve site-level bottlenecks to ensure steady progress of the remaining work. We are now actively focused on accelerating the balance construction activities and coordinating…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Feriha Heights in Wadala, Shiwar, Nashik is P51600055909.

Is Feriha Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights is registered as P51600055909 and its status is "Registered and active".

What is the construction status of Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Feriha Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Feriha Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Feriha Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights is registered on MahaRERA as P51600055909, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Feriha Heights's possession date changes?

The latest dates are on Feriha Heights's MahaRERA page (P51600055909). GharKundli's Kundli Watch sends a free WhatsApp update on Feriha Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Feriha Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights has one building filed: Feriha Heights with 8 floors and 28 units.

How big is the land of Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights stands on 530 sq m of land (about 0.1 acres), with 1,658 sq m of sanctioned built-up area.

What is the track record of Feriha Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aroma Developers (a group of 5 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Feriha Heights?

Google Maps has reviews of Feriha Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Feriha Heights?

Feriha Heights by Aroma Developers is in Wadala, Shiwar, Nashik (pincode 422007), Maharashtra, and is registered on MahaRERA as P51600055909, per GharKundli's check of MahaRERA records.

How many homes are in Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights has 24 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.

When was Feriha Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Feriha Heights was registered on MahaRERA on 29 April 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Feriha Heights?

No court cases are listed for Feriha Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Feriha Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aroma Developers.

All projects with possession due in 2027 in Nashik →

Other projects in Nashik

All 87 projects in Industrial Estate (422007) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.