Skip to content
GharKundli

Vastu Avenue

by Apurva Builders & Developers · Dhruv Nagar, Nashik

Possession: Vastu Avenue is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600051304. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Vastu Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vastu Avenue has moved

  1. 30 April 2025

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EA05062501446)

    Reason the builder gave MahaRERA:
    “a) There is one Building in a project. We have already completed the construction for the said Buildings in accordance with the terms and conditions of commencement certificate and are in the process of obtaining completion certificate from…” Read the full reason“a) There is one Building in a project. We have already completed the construction for the said Buildings in accordance with the terms and conditions of commencement certificate and are in the process of obtaining completion certificate from Nashik Municipal Corporation. b) We are targeting to obtain the occupancy certificate from the local authority by 31.12.2025.”
  3. 15 August 2026

    Extended at the builder's request (MahaRERA application EA24042620727)

    Reason the builder gave MahaRERA:
    “1. We have completed the said project and obtained a full occupancy certificate from Nashik Municipal Corporation; Nashik dated 25.02.2026. The copy of the same is attached herewith. 1. Since the project completion date on RERA portal is 31…” Read the full reason“1. We have completed the said project and obtained a full occupancy certificate from Nashik Municipal Corporation; Nashik dated 25.02.2026. The copy of the same is attached herewith. 1. Since the project completion date on RERA portal is 31.12.2025, we are applying for extension till 15.08.2026 only for filing application for correction to update updated estimated cost of project.”

Source: Vastu Avenue’s extension records on MahaRERA (P51600051304), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vastu Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600051304
Status
Completed
Builder
Apurva Builders & Developers
Location
Dhruv Nagar, Nashik · 422007
Project type
Others
Registered on
8 Jun 2023
Completion date at registration
April 2025
Latest completion date
August 2026
Delay so far
16 months
Homes
22
Sold or booked
76%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Vastu Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vastu Avenue100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Vastu Avenue: covers Ground + Four Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vastu Avenue every month.

Vastu Avenue: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vastu Avenue (5 floors, 37 units)
  • Car parking: 14 covered
  • Land: 1,115 sq m (about 0.3 acres) · sanctioned built-up 2,080 sq m

The builder’s record and reviews

Apurva Builders & Developers has 7 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Vastu Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vastu Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vastu Avenue

What is the possession date of Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vastu Avenue in Dhruv Nagar, Nashik is 15 August 2026 — 16 months later than 30 April 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Vastu Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vastu Avenue's builder has filed on MahaRERA, the official one, is 15 August 2026, already 16 months later than the 30 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vastu Avenue extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "a) There is one Building in a project. We have already completed the construction for the said Buildings in accordance with the terms and conditions of commencement certificate and are in the process of obtaining completion certificate from Nashik Municipal Corporation. b) We are targeting to obtain the occupancy certificate from the local authority by 31.12.2025."; to 15 August 2026, giving the reason "1. We have completed the said project and obtained a full occupancy certificate from Nashik Municipal Corporation; Nashik dated 25.02.2026. The copy of the same is attached herewith. 1. Since the project completion date on RERA portal is 31.12.2025, we are applying for extension till 15.08.2026 only for filing application for correction to update updated estimated cost of project.".

What is the RERA number of Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vastu Avenue in Dhruv Nagar, Nashik is P51600051304.

Is Vastu Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue is registered as P51600051304 and its status is "Completed".

What is the construction status of Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue's status on MahaRERA is "Completed". As filed by the builder, slab work on Vastu Avenue is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vastu Avenue have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vastu Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue is registered on MahaRERA as P51600051304, its MahaRERA status is "Completed", its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Vastu Avenue's possession date changes?

The latest dates are on Vastu Avenue's MahaRERA page (P51600051304). GharKundli's Kundli Watch sends a free WhatsApp update on Vastu Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vastu Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue has one building filed: Vastu Avenue with 5 floors and 37 units.

How much parking does Vastu Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Vastu Avenue.

How big is the land of Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue stands on 1,115 sq m of land (about 0.3 acres), with 2,080 sq m of sanctioned built-up area.

What is the track record of Vastu Avenue's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Apurva Builders & Developers has 7 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vastu Avenue?

Google Maps has reviews of Vastu Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vastu Avenue?

Vastu Avenue by Apurva Builders & Developers is in Dhruv Nagar, Nashik (pincode 422007), Maharashtra, and is registered on MahaRERA as P51600051304, per GharKundli's check of MahaRERA records.

How many homes are in Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue has 22 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.

When was Vastu Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Avenue was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Vastu Avenue?

No court cases are listed for Vastu Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Vastu Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Apurva Builders & Developers, which has 2 other projects registered on MahaRERA.

Other projects in Nashik

All 87 projects in Industrial Estate (422007) →

Other projects by Apurva Builders & Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.