Vastu Shilp
by Apurva Builders & Developers · Gangapur Gaon, Gangapur Road, Nashik
Possession date of Vastu Shilp: 30 April 2029, moved from 31 December 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600052520, and currently active. Its completion date has moved from December 2026 to April 2029: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vastu Shilp?
How the possession date of Vastu Shilp has moved
31 December 2026
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EA20032620294)
Reason the builder gave MahaRERA:
“a) The original Commencement Certificate and Approved Plan dated 30.05.2023 were sanctioned for construction of Basement + Ground/Stilt Floor + 3 Habitable Floors for Wing A and Wing B, comprising 60 residential units. b) Subsequently, we o…” Read the full reason
“a) The original Commencement Certificate and Approved Plan dated 30.05.2023 were sanctioned for construction of Basement + Ground/Stilt Floor + 3 Habitable Floors for Wing A and Wing B, comprising 60 residential units. b) Subsequently, we obtained a Revised Commencement Certificate and Approved Plan dated 19.11.2025 from Nashik Municipal Corporation for construction of Basement + Ground/Stilt Floor + 7 Habitable Floors for Wing A and Wing B. Pursuant to this revision, the total number of residential units has increased from 60 to 116 units. c) The increase in number of floors and units has…”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vastu Shilp’s extension records on MahaRERA (P51600052520), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vastu Shilp
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600052520
- Status
- Registered and active
- Builder
- Apurva Builders & Developers
- Location
- Gangapur Gaon, Gangapur Road, Nashik · 422003
- Project type
- Others
- Registered on
- 8 Sep 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2029
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 97
- Sold or booked
- 40%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Vastu Shilp, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vastu Shilp Wing A | 100% | 100% | 70% | 0% |
| Vastu Shilp Wing B | 100% | 100% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vastu Shilp Wing A: covers Basement+ Ground/Stilt+7 Habitable Floors
- Vastu Shilp Wing B: covers Basement+ Ground/Stilt+7 Habitable Floors
Latest CC order on MahaRERA: dated 19/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vastu Shilp every month.
Vastu Shilp: buildings, flats and land, as filed on MahaRERA
- Buildings: Vastu Shilp Wing A (9 floors, 55 units) · Vastu Shilp Wing B (9 floors, 61 units)
- Car parking: 38 covered, 14 open
- Land: 2,300 sq m (about 0.6 acres) · sanctioned built-up 6,665 sq m
- Boundaries filed include: Road and Canal
The builder’s record and reviews
Apurva Builders & Developers has 7 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Vastu Shilp →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vastu Shilp: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vastu Shilp
What is the possession date of Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vastu Shilp in Gangapur Gaon, Gangapur Road, Nashik is 30 April 2029 — 24 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vastu Shilp?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vastu Shilp's builder has filed on MahaRERA, the official one, is 30 April 2029, already 24 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vastu Shilp extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "a) The original Commencement Certificate and Approved Plan dated 30.05.2023 were sanctioned for construction of Basement + Ground/Stilt Floor + 3 Habitable Floors for Wing A and Wing B, comprising 60 residential units. b) Subsequently, we obtained a Revised Commencement Certificate and Approved Plan dated 19.11.2025 from Nashik Municipal Corporation for construction of Basement + Ground/Stilt Floor + 7 Habitable Floors for Wing A and Wing B. Pursuant to this revision, the total number of residential units has increased from 60 to 116 units. c) The increase in number of floors and units has…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vastu Shilp in Gangapur Gaon, Gangapur Road, Nashik is P51600052520.
Is Vastu Shilp registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp is registered as P51600052520 and its status is "Registered and active".
What is the construction status of Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Vastu Shilp have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vastu Shilp safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp is registered on MahaRERA as P51600052520, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vastu Shilp's possession date changes?
The latest dates are on Vastu Shilp's MahaRERA page (P51600052520). GharKundli's Kundli Watch sends a free WhatsApp update on Vastu Shilp every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vastu Shilp have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp has 2 buildings filed: Vastu Shilp Wing A with 9 floors and 55 units; Vastu Shilp Wing B with 9 floors and 61 units.
How much parking does Vastu Shilp have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 38 covered and 14 open car parking spaces for Vastu Shilp.
How big is the land of Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp stands on 2,300 sq m of land (about 0.6 acres), with 6,665 sq m of sanctioned built-up area.
What is the track record of Vastu Shilp's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Apurva Builders & Developers has 7 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vastu Shilp?
Google Maps has reviews of Vastu Shilp written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vastu Shilp?
Vastu Shilp by Apurva Builders & Developers is in Gangapur Gaon, Gangapur Road, Nashik (pincode 422003), Maharashtra, and is registered on MahaRERA as P51600052520, per GharKundli's check of MahaRERA records. Its boundaries filed there include Road and Canal.
How many homes are in Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp has 97 homes in 2 towers registered on MahaRERA, and 40% of them are sold or booked.
When was Vastu Shilp registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastu Shilp was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Vastu Shilp?
No court cases are listed for Vastu Shilp on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Vastu Shilp?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Apurva Builders & Developers, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vastu Shilp
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Other projects by Apurva Builders & Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.