Bishopsgate
by Bridgeview Real Estate Development LLP · Malabar Cumballa Hill, MumbaiAlso near Tardeo, Malabar Hill, Tulsiwadi
Possession: Bishopsgate is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900001325. Status: Completed. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Bishopsgate?
How the possession date of Bishopsgate has moved
30 September 2019
Completion date given when the project was registered
29 September 2020
Extended at the builder's request (MahaRERA application EXT51900002415)
Reason the builder gave MahaRERA:
“A. Issues faced by the Promoter, due to the restrictions imposed by the Regional Transport Office, Tardeo, Mumbai (“RTO”) on use of heavy vehicles, by the civil work contractor, appointed by the Promoter to construct the Project and supply…” Read the full reason
“A. Issues faced by the Promoter, due to the restrictions imposed by the Regional Transport Office, Tardeo, Mumbai (“RTO”) on use of heavy vehicles, by the civil work contractor, appointed by the Promoter to construct the Project and supply materials required for construction. B. Force majeure conditions due to heavy rains in Mumbai during rainy season of the years 2017, 2018 and 2019, the Promoter faced many issues while developing the Project.”29 March 2021
Revised completion date on MahaRERA
Source: Bishopsgate’s extension records on MahaRERA (P51900001325), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bishopsgate
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the March 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001325
- Status
- Completed
- Builder
- Bridgeview Real Estate Development LLP
- Location
- Malabar Cumballa Hill, Mumbai · 400026
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- September 2019
- Latest completion date
- March 2021
- Delay so far
- 18 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Appeals at the tribunal
- 5
- Title report on file
- Not found
Construction progress of Bishopsgate, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bishopsgate | 100% | 100% | 75% | 64% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bishopsgate every month.
Bishopsgate: buildings, flats and land, as filed on MahaRERA
- Buildings: Bishopsgate (42 floors)
- Land: 1,968 sq m (about 0.5 acres) · sanctioned built-up 3,432 sq m · recreational space 295 sq m
- Boundaries filed include: setback of Sophia College Road, Bhulabhai Desai Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bishopsgate →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bishopsgate: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bishopsgate
What is the possession date of Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bishopsgate in Malabar Cumballa Hill, Mumbai is 29 March 2021 — 18 months later than 30 September 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Bishopsgate?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bishopsgate's builder has filed on MahaRERA, the official one, is 29 March 2021, already 18 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bishopsgate extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate's builder applied to MahaRERA to extend the completion date once: to 29 September 2020, giving the reason "A. Issues faced by the Promoter, due to the restrictions imposed by the Regional Transport Office, Tardeo, Mumbai (“RTO”) on use of heavy vehicles, by the civil work contractor, appointed by the Promoter to construct the Project and supply materials required for construction. B. Force majeure conditions due to heavy rains in Mumbai during rainy season of the years 2017, 2018 and 2019, the Promoter faced many issues while developing the Project.".
What is the RERA number of Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bishopsgate in Malabar Cumballa Hill, Mumbai is P51900001325.
Is Bishopsgate registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate is registered as P51900001325 and its status is "Completed".
What is the construction status of Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate's status on MahaRERA is "Completed". As filed by the builder, slab work on Bishopsgate is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does Bishopsgate have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bishopsgate safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate is registered on MahaRERA as P51900001325, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bishopsgate's possession date changes?
The latest dates are on Bishopsgate's MahaRERA page (P51900001325). GharKundli's Kundli Watch sends a free WhatsApp update on Bishopsgate every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bishopsgate have?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate has one building filed: Bishopsgate with 42 floors.
How big is the land of Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate stands on 1,968 sq m of land (about 0.5 acres), with 3,432 sq m of sanctioned built-up area and 295 sq m of recreational open space.
Where can I read reviews of Bishopsgate?
Google Maps has reviews of Bishopsgate written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bishopsgate?
Bishopsgate by Bridgeview Real Estate Development LLP is in Malabar Cumballa Hill, Mumbai (pincode 400026), near Tardeo, Malabar Hill, Tulsiwadi, Maharashtra, and is registered on MahaRERA as P51900001325, per GharKundli's check of MahaRERA records. Its boundaries filed there include setback of Sophia College Road, Bhulabhai Desai Road.
How many homes are in Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate has 12 homes in 1 tower registered on MahaRERA.
When was Bishopsgate registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bishopsgate was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bishopsgate?
No court cases are listed for Bishopsgate on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Bishopsgate?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Bridgeview Real Estate Development LLP.
Check it yourself on MahaRERA
- How to check the possession date of Bishopsgate
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400026
All 15 projects in Cumballa Hill (400026) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.