Carmichael Residences
by R A Realty Ventures LLP · Malabar Cumballa Hill, MumbaiAlso near Tardeo, Malabar Hill, mumbai central
Possession: Carmichael Residences is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900001442. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Carmichael Residences?
How the possession date of Carmichael Residences has moved
30 September 2018
Completion date given when the project was registered
30 September 2019
Extended at the builder's request (MahaRERA application EXT51900000646)
Reason the builder gave MahaRERA:
“Detailed application for extention is uploded hereunder along with documents supporting the grounds and reasons thereof. the three main reasons for which extension of Registration is sought: A. Issues with adjoining society namely, Anand Ka…” Read the full reason
“Detailed application for extention is uploded hereunder along with documents supporting the grounds and reasons thereof. the three main reasons for which extension of Registration is sought: A. Issues with adjoining society namely, Anand Kamal Co-operative Housing Society Ltd (“Society”), in relation to relocation of pipelines supplying drinking water, pump room and sewerage lines of the Society. These pipelines and pump room were, at the relevant time, located on our project where the proposed Storm water drainage pipeline and Sewer pipeline connections of Promoter’s project were to be con…”
Source: Carmichael Residences’s extension records on MahaRERA (P51900001442), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Carmichael Residences
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the September 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001442
- Status
- Completed
- Builder
- R A Realty Ventures LLP
- Location
- Malabar Cumballa Hill, Mumbai · 400026
- Project type
- Residential / Group Housing
- Registered on
- 28 Jul 2017
- Completion date at registration
- September 2018
- Latest completion date
- September 2019
- Delay so far
- 12 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
Construction progress of Carmichael Residences, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Carmichael Residences | 100% | 100% | 96% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Carmichael Residences every month.
Carmichael Residences: buildings, flats and land, as filed on MahaRERA
- Buildings: Carmichael Residences (29 floors)
- Land: 2,017 sq m (about 0.5 acres) · sanctioned built-up 9,022 sq m · recreational space 161 sq m
- Boundaries filed include: Setback of Carmichael Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Carmichael Residences →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Carmichael Residences: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Carmichael Residences
What is the possession date of Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Carmichael Residences in Malabar Cumballa Hill, Mumbai is 30 September 2019 — 12 months later than 30 September 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Carmichael Residences?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Carmichael Residences's builder has filed on MahaRERA, the official one, is 30 September 2019, already 12 months later than the 30 September 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Carmichael Residences extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences's builder applied to MahaRERA to extend the completion date once: to 30 September 2019, giving the reason "Detailed application for extention is uploded hereunder along with documents supporting the grounds and reasons thereof. the three main reasons for which extension of Registration is sought: A. Issues with adjoining society namely, Anand Kamal Co-operative Housing Society Ltd (“Society”), in relation to relocation of pipelines supplying drinking water, pump room and sewerage lines of the Society. These pipelines and pump room were, at the relevant time, located on our project where the proposed Storm water drainage pipeline and Sewer pipeline connections of Promoter’s project were to be con…".
What is the RERA number of Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Carmichael Residences in Malabar Cumballa Hill, Mumbai is P51900001442.
Is Carmichael Residences registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences is registered as P51900001442 and its status is "Completed".
What is the construction status of Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences's status on MahaRERA is "Completed". As filed by the builder, slab work on Carmichael Residences is 100% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.
Does Carmichael Residences have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Carmichael Residences safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences is registered on MahaRERA as P51900001442, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Carmichael Residences's possession date changes?
The latest dates are on Carmichael Residences's MahaRERA page (P51900001442). GharKundli's Kundli Watch sends a free WhatsApp update on Carmichael Residences every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Carmichael Residences have?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences has one building filed: Carmichael Residences with 29 floors.
How big is the land of Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences stands on 2,017 sq m of land (about 0.5 acres), with 9,022 sq m of sanctioned built-up area and 161 sq m of recreational open space.
Where can I read reviews of Carmichael Residences?
Google Maps has reviews of Carmichael Residences written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Carmichael Residences?
Carmichael Residences by R A Realty Ventures LLP is in Malabar Cumballa Hill, Mumbai (pincode 400026), near Tardeo, Malabar Hill, mumbai central, Maharashtra, and is registered on MahaRERA as P51900001442, per GharKundli's check of MahaRERA records. Its boundaries filed there include Setback of Carmichael Road.
How many homes are in Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences has 28 homes in 1 tower registered on MahaRERA.
When was Carmichael Residences registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Carmichael Residences was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Carmichael Residences?
2 court cases are listed for Carmichael Residences on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Carmichael Residences?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is R A Realty Ventures LLP.
Check it yourself on MahaRERA
- How to check the possession date of Carmichael Residences
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400026
All 15 projects in Cumballa Hill (400026) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.