NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13
by SHIVAM PARIVAR DEVELOPERS PVT LTD · Goregaon west, MumbaiAlso near Goregaon East, Cama Estate, Dindoshi, Malad East
Possession date of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13: 30 December 2025, moved from 30 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800011447. Status: Lapsed (registration period ended). 15 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
GharKundli’s full report on NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 15 complaints and 5 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011447
- Status
- Lapsed (registration period ended)
- Builder
- SHIVAM PARIVAR DEVELOPERS PVT LTD
- Location
- Goregaon west, Mumbai · 400062
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 390
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 15
- Court cases listed
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRLON EMPLOYEES CHS LTD | 100% | 62% | 51% | 2% |
Commencement certificate (CC), as filed on MahaRERA
- NIRLON EMPLOYEES CHS LTD: covers 28 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 every month.
NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 448 – 456 | 200 |
| 2 BHK | 490 – 563 | 190 |
| Office Space | 142 – 4,260 | 20 |
| Shops | 85 – 412 | 11 |
- Buildings: NIRLON EMPLOYEES CHS LTD (28 floors, 421 units)
- Land: 2,454 sq m (about 0.6 acres) · sanctioned built-up 6,528 sq m
- Boundaries filed include: VIVEK VIDAYALAYA MARG, SHRIRANG SABLE MARG, OFF S V ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13
What is the possession date of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 in Goregaon west, Mumbai is 30 December 2025 — 12 months later than 30 December 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 in Goregaon west, Mumbai is P51800011447.
Is NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 is registered as P51800011447 and its status is "Lapsed (registration period ended)".
What is the construction status of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRLON EMPLOYEES CHS LTD is 62% done and internal work 51%. GharKundli's full report compares construction progress with the deadline.
Does NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 have complaints on MahaRERA?
15 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 is registered on MahaRERA as P51800011447, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 15 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13's possession date changes?
The latest dates are on NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13's MahaRERA page (P51800011447). GharKundli's Kundli Watch sends a free WhatsApp update on NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 have?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 has one building filed: NIRLON EMPLOYEES CHS LTD with 28 floors and 421 units.
What are the flat sizes (carpet area) in NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13: 1 BHK: 448 to 456 sq ft carpet (200 homes); 2 BHK: 490 to 563 sq ft carpet (190 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 stands on 2,454 sq m of land (about 0.6 acres), with 6,528 sq m of sanctioned built-up area.
What is the track record of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
Google Maps has reviews of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 15 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 by SHIVAM PARIVAR DEVELOPERS PVT LTD is in Goregaon west, Mumbai (pincode 400062), near Goregaon East, Cama Estate, Dindoshi, Malad East, Maharashtra, and is registered on MahaRERA as P51800011447, per GharKundli's check of MahaRERA records. Its boundaries filed there include VIVEK VIDAYALAYA MARG, SHRIRANG SABLE MARG, OFF S V ROAD.
How many homes are in NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 has 390 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
5 court cases are listed for NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVAM PARIVAR DEVELOPERS PVT LTD, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All Borivali projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.