Possession date of SHRI YAMAI KRUPA: 30 October 2022, moved from 31 March 2018 (55 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800014999. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2022) has passed.

What do you want to know about SHRI YAMAI KRUPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI YAMAI KRUPA has moved

  1. 31 March 2018

    Completion date given when the project was registered

  2. 31 March 2019

    Extended at the builder's request (MahaRERA application EXT51800000780)

    Reason the builder gave MahaRERA:
    “WE HAD OBTAINED RERA REGISTRATION FOR SHRI YAMAI KRUPA PROJECT UNDER P51800014999 DATED 22.01.2018 AND REGISTRATION AS VALID TILL ATE 31.03.2018 BUT DUE TO WORK HAS BEEN DELAYED DUE TO NON PAYMENT FROM PURCHASERS OF FLAT AND PENDING APPROVA…” Read the full reason“WE HAD OBTAINED RERA REGISTRATION FOR SHRI YAMAI KRUPA PROJECT UNDER P51800014999 DATED 22.01.2018 AND REGISTRATION AS VALID TILL ATE 31.03.2018 BUT DUE TO WORK HAS BEEN DELAYED DUE TO NON PAYMENT FROM PURCHASERS OF FLAT AND PENDING APPROVALS BY COMPETENT AUTHORITIES.THE PROJECT COMPRISE OF ONE BUILDING AND TILL DATE MORE THAN 95 % OF THE WORK OF THE BUILDING COMPLETED.”
  3. 30 October 2022

    Extended at the builder's request (MahaRERA application EXT51800011781)

    Reason the builder gave MahaRERA:
    “The Project Comprises of one building. The Work has been delayed due to Non-payment from flat purchases and pending approvals from competent authorities. We are in the process of completing compliances necessary for obtaining occupation cer…” Read the full reason“The Project Comprises of one building. The Work has been delayed due to Non-payment from flat purchases and pending approvals from competent authorities. We are in the process of completing compliances necessary for obtaining occupation certificate. The Covid 19 Pandemic also caused delay in completing the Project.”

Source: SHRI YAMAI KRUPA’s extension records on MahaRERA (P51800014999), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI YAMAI KRUPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the October 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014999
Status
Lapsed (registration period ended)
Builder
JEEVANDEEP DEVELOPERS
Location
Boriwali, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
22 Jan 2018
Completion date at registration
March 2018
Latest completion date
October 2022
Delay so far
55 months
Homes
18
Towers
1
Complaints on MahaRERA
6
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SHRI YAMAI KRUPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHRI YAMAI KRUPA100%100%95%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI YAMAI KRUPA every month.

SHRI YAMAI KRUPA: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHRI YAMAI KRUPA (20 floors)
  • Land: 481 sq m (about 0.1 acres) · sanctioned built-up 1,997 sq m

The builder’s record and reviews

Jeevandeep Developers has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 87 months late); 1 lapsed. 6 complaints on MahaRERA across 1 project.

Read Google reviews of SHRI YAMAI KRUPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI YAMAI KRUPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI YAMAI KRUPA

What is the possession date of SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRI YAMAI KRUPA in Boriwali, Mumbai is 30 October 2022 — 55 months later than 31 March 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHRI YAMAI KRUPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI YAMAI KRUPA's builder has filed on MahaRERA, the official one, is 30 October 2022, already 55 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI YAMAI KRUPA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2019, giving the reason "WE HAD OBTAINED RERA REGISTRATION FOR SHRI YAMAI KRUPA PROJECT UNDER P51800014999 DATED 22.01.2018 AND REGISTRATION AS VALID TILL ATE 31.03.2018 BUT DUE TO WORK HAS BEEN DELAYED DUE TO NON PAYMENT FROM PURCHASERS OF FLAT AND PENDING APPROVALS BY COMPETENT AUTHORITIES.THE PROJECT COMPRISE OF ONE BUILDING AND TILL DATE MORE THAN 95 % OF THE WORK OF THE BUILDING COMPLETED."; to 30 October 2022, giving the reason "The Project Comprises of one building. The Work has been delayed due to Non-payment from flat purchases and pending approvals from competent authorities. We are in the process of completing compliances necessary for obtaining occupation certificate. The Covid 19 Pandemic also caused delay in completing the Project.".

What is the RERA number of SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRI YAMAI KRUPA in Boriwali, Mumbai is P51800014999.

Is SHRI YAMAI KRUPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA is registered as P51800014999 and its status is "Lapsed (registration period ended)".

What is the construction status of SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHRI YAMAI KRUPA is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does SHRI YAMAI KRUPA have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHRI YAMAI KRUPA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA is registered on MahaRERA as P51800014999, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 55 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI YAMAI KRUPA's possession date changes?

The latest dates are on SHRI YAMAI KRUPA's MahaRERA page (P51800014999). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI YAMAI KRUPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI YAMAI KRUPA have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA has one building filed: SHRI YAMAI KRUPA with 20 floors.

How big is the land of SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA stands on 481 sq m of land (about 0.1 acres), with 1,997 sq m of sanctioned built-up area.

What is the track record of SHRI YAMAI KRUPA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jeevandeep Developers has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 87 months late); 1 lapsed. 6 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHRI YAMAI KRUPA?

Google Maps has reviews of SHRI YAMAI KRUPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI YAMAI KRUPA?

SHRI YAMAI KRUPA by JEEVANDEEP DEVELOPERS is in Boriwali, Mumbai (pincode 400016), Maharashtra, and is registered on MahaRERA as P51800014999, per GharKundli's check of MahaRERA records.

How many homes are in SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA has 18 homes in 1 tower registered on MahaRERA.

When was SHRI YAMAI KRUPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI YAMAI KRUPA was registered on MahaRERA on 22 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI YAMAI KRUPA?

No court cases are listed for SHRI YAMAI KRUPA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHRI YAMAI KRUPA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JEEVANDEEP DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in Borivali

All 83 projects in Mahim (400016) →

Other projects by JEEVANDEEP DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.