Lifescapes Kshitij
by Roxina Real Estate Pvt. Ltd. · Bhuleshwar, MumbaiAlso near Girgaon, Khetwadi, Grant Road
Possession date of Lifescapes Kshitij: 30 March 2027, moved from 30 December 2023 (35 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900004172, and currently active. Its completion date has moved from December 2023 to March 2027: 35 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Lifescapes Kshitij?
How the possession date of Lifescapes Kshitij has moved
30 December 2023
Completion date given when the project was registered
29 November 2024
Extended at the builder's request (MahaRERA application EXT51900018579)
Reason the builder gave MahaRERA:
“Construction activity of Project Lifescapes Kshitij had slowed down and had significant impact on the project progress due to Covid-19 Pandemic lockdown from period March 2020 to March 2021. There was shortage of labour and material supply…” Read the full reason
“Construction activity of Project Lifescapes Kshitij had slowed down and had significant impact on the project progress due to Covid-19 Pandemic lockdown from period March 2020 to March 2021. There was shortage of labour and material supply during the above mentioned lockdown period. As a cascading effect, the project execution suffered, impacting the completion before 30/12/2023. Roxina Real Estate Pvt. Ltd. is hence seeking one year extension under Sec 6 of RERA Act to complete the balance work of project Lifescapes Kshitij.”30 November 2026
Extended at the builder's request (MahaRERA application EXT51900027476)
Reason the builder gave MahaRERA:
“We are seeking an extension for the completion of the Lifescapes Kshitij project, under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016, due to the unforeseen delays encountered during the construction process. Despit…” Read the full reason
“We are seeking an extension for the completion of the Lifescapes Kshitij project, under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016, due to the unforeseen delays encountered during the construction process. Despite our best efforts, several challenges have impacted the original timeline, and we would like to highlight the key reasons for the delay: 1. Contractor Discontinuation: Two major contractors were discontinued from the project, resulting in significant delays in appointing new contractors and finalizing the terms of their engagement. Additionally, the proc…”30 March 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lifescapes Kshitij’s extension records on MahaRERA (P51900004172), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lifescapes Kshitij
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 6 court cases, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900004172
- Status
- Registered and active
- Builder
- Roxina Real Estate Pvt. Ltd.
- Location
- Bhuleshwar, Mumbai · 400002
- Project type
- Residential / Group Housing
- Registered on
- 8 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- March 2027
- Delay so far
- 35 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 213
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 6
- Title report on file
- Not found
Construction progress of Lifescapes Kshitij, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Lifescapes Kshitij | 100% | 53% | 20% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lifescapes Kshitij every month.
Lifescapes Kshitij: buildings, flats and land, as filed on MahaRERA
- Buildings: Lifescapes Kshitij (54 floors)
- Land: 5,811 sq m (about 1.4 acres) · sanctioned built-up 15,263 sq m · recreational space 1,069 sq m
- Boundaries filed include: Babasaheb Jaykar Marg, K M Zaveri Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Lifescapes Kshitij →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lifescapes Kshitij: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lifescapes Kshitij
What is the possession date of Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lifescapes Kshitij in Bhuleshwar, Mumbai is 30 March 2027 — 35 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Lifescapes Kshitij?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lifescapes Kshitij's builder has filed on MahaRERA, the official one, is 30 March 2027, already 35 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lifescapes Kshitij extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij's builder applied to MahaRERA to extend the completion date 2 times: to 29 November 2024, giving the reason "Construction activity of Project Lifescapes Kshitij had slowed down and had significant impact on the project progress due to Covid-19 Pandemic lockdown from period March 2020 to March 2021. There was shortage of labour and material supply during the above mentioned lockdown period. As a cascading effect, the project execution suffered, impacting the completion before 30/12/2023. Roxina Real Estate Pvt. Ltd. is hence seeking one year extension under Sec 6 of RERA Act to complete the balance work of project Lifescapes Kshitij."; to 30 November 2026, giving the reason "We are seeking an extension for the completion of the Lifescapes Kshitij project, under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016, due to the unforeseen delays encountered during the construction process. Despite our best efforts, several challenges have impacted the original timeline, and we would like to highlight the key reasons for the delay: 1. Contractor Discontinuation: Two major contractors were discontinued from the project, resulting in significant delays in appointing new contractors and finalizing the terms of their engagement. Additionally, the proc…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lifescapes Kshitij in Bhuleshwar, Mumbai is P51900004172.
Is Lifescapes Kshitij registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij is registered as P51900004172 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Lifescapes Kshitij is 53% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does Lifescapes Kshitij have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Lifescapes Kshitij safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij is registered on MahaRERA as P51900004172, its completion date has moved 35 months since registration, 2 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lifescapes Kshitij's possession date changes?
The latest dates are on Lifescapes Kshitij's MahaRERA page (P51900004172). GharKundli's Kundli Watch sends a free WhatsApp update on Lifescapes Kshitij every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lifescapes Kshitij have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij has one building filed: Lifescapes Kshitij with 54 floors.
How big is the land of Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij stands on 5,811 sq m of land (about 1.4 acres), with 15,263 sq m of sanctioned built-up area and 1,069 sq m of recreational open space.
Where can I read reviews of Lifescapes Kshitij?
Google Maps has reviews of Lifescapes Kshitij written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lifescapes Kshitij?
Lifescapes Kshitij by Roxina Real Estate Pvt. Ltd. is in Bhuleshwar, Mumbai (pincode 400002), near Girgaon, Khetwadi, Grant Road, Maharashtra, and is registered on MahaRERA as P51900004172, per GharKundli's check of MahaRERA records. Its boundaries filed there include Babasaheb Jaykar Marg, K M Zaveri Marg.
How many homes are in Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij has 213 homes in 1 tower registered on MahaRERA.
When was Lifescapes Kshitij registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lifescapes Kshitij was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Lifescapes Kshitij?
6 court cases are listed for Lifescapes Kshitij on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Lifescapes Kshitij?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Roxina Real Estate Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of Lifescapes Kshitij
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Bhuleshwar
All 32 projects in Kalbadevi (400002) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.