AGARWAL FLORENCE

by PARAM ANAND BUILDERS LLP (Riddhi) · Goregaon West, MumbaiAlso near Malad East, Goregaon East, Motilal Nagar

Possession date of AGARWAL FLORENCE: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800032916, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AGARWAL FLORENCE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AGARWAL FLORENCE has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA14112518326)

    Reason the builder gave MahaRERA:
    “We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the fol…” Read the full reason“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and r…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA26062621550)

    Reason the builder gave MahaRERA:
    “We, PARAM ANAND BUILDERS LLP, are the promoters of the real estate project known as "AGARWAL FLORENCE" bearing MahaRERA Registration No. P51800032916. We would like to respectfully bring to your attention that the project has encountered ce…” Read the full reason“We, PARAM ANAND BUILDERS LLP, are the promoters of the real estate project known as "AGARWAL FLORENCE" bearing MahaRERA Registration No. P51800032916. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: Delay in Statutory Clearances/Utility Approvals The CFO NOC had to be procured from Fire and Safety department and other government authorities which led to a delay in the comp…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AGARWAL FLORENCE’s extension records on MahaRERA (P51800032916), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AGARWAL FLORENCE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800032916
Status
Registered and active
Builder
PARAM ANAND BUILDERS LLP
Location
Goregaon West, Mumbai · 400062
Project type
Residential / Group Housing
Registered on
2 Feb 2022
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
146
Sold or booked
42%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of AGARWAL FLORENCE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A AND B100%100%95%95%

Commencement certificate (CC), as filed on MahaRERA

  • WING A AND B: covers Wing `A' & `B' comprising of Stilt (for mechanized parking) + 1st to 19th upper floors + Lifts opening at Terrace + OHT in Wing `A' & 1st to19th + 20th (Part) u

Latest CC order on MahaRERA: dated 30/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AGARWAL FLORENCE every month.

AGARWAL FLORENCE: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A AND B (21 floors, 146 units)
  • Car parking: 154 covered, 1 open
  • Land: 4,151 sq m (about 1.0 acres) · sanctioned built-up 11,198 sq m · recreational space 789 sq m

The builder’s record and reviews

Homewell Realty (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 47 complaints on MahaRERA across 4 projects.

Read Google reviews of AGARWAL FLORENCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AGARWAL FLORENCE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AGARWAL FLORENCE

What is the possession date of AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AGARWAL FLORENCE in Goregaon West, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AGARWAL FLORENCE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AGARWAL FLORENCE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AGARWAL FLORENCE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and r…"; to 31 December 2026, giving the reason "We, PARAM ANAND BUILDERS LLP, are the promoters of the real estate project known as "AGARWAL FLORENCE" bearing MahaRERA Registration No. P51800032916. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: Delay in Statutory Clearances/Utility Approvals The CFO NOC had to be procured from Fire and Safety department and other government authorities which led to a delay in the comp…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AGARWAL FLORENCE in Goregaon West, Mumbai is P51800032916.

Is AGARWAL FLORENCE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE is registered as P51800032916 and its status is "Registered and active".

What is the construction status of AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING A AND B is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does AGARWAL FLORENCE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AGARWAL FLORENCE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE is registered on MahaRERA as P51800032916, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AGARWAL FLORENCE's possession date changes?

The latest dates are on AGARWAL FLORENCE's MahaRERA page (P51800032916). GharKundli's Kundli Watch sends a free WhatsApp update on AGARWAL FLORENCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AGARWAL FLORENCE have?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE has one building filed: WING A AND B with 21 floors and 146 units.

How much parking does AGARWAL FLORENCE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 154 covered and 1 open car parking spaces for AGARWAL FLORENCE.

How big is the land of AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE stands on 4,151 sq m of land (about 1.0 acres), with 11,198 sq m of sanctioned built-up area and 789 sq m of recreational open space.

What is the track record of AGARWAL FLORENCE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Homewell Realty (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 47 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AGARWAL FLORENCE?

Google Maps has reviews of AGARWAL FLORENCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AGARWAL FLORENCE?

AGARWAL FLORENCE by PARAM ANAND BUILDERS LLP (Riddhi) is in Goregaon West, Mumbai (pincode 400062), near Malad East, Goregaon East, Motilal Nagar, Maharashtra, and is registered on MahaRERA as P51800032916, per GharKundli's check of MahaRERA records.

How many homes are in AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE has 146 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.

When was AGARWAL FLORENCE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AGARWAL FLORENCE was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on AGARWAL FLORENCE?

No court cases are listed for AGARWAL FLORENCE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AGARWAL FLORENCE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARAM ANAND BUILDERS LLP, the company Riddhi files this project under.