SHREEPATI BAYVIEW
by SHREEPATI BUILD INFRA INVESTMENT LIMITED · Nana Chowk, MumbaiAlso near Girgaon, Khetwadi, Grant Road
Possession date of SHREEPATI BAYVIEW: 30 December 2026. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900010019. Status: De-Registered. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
Deregistered by MahaRERA
MahaRERA has deregistered this project by order. Builders often apply for this themselves when a project doesn't go ahead -- read the order before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list Read the order
What do you want to know about SHREEPATI BAYVIEW?
GharKundli’s full report on SHREEPATI BAYVIEW
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900010019
- Status
- De-Registered
- Builder
- SHREEPATI BUILD INFRA INVESTMENT LIMITED
- Location
- Nana Chowk, Mumbai · 400004
- Project type
- Residential / Group Housing
- Registered on
- 23 Aug 2017
- Completion date at registration
- December 2026
- Latest completion date
- December 2026
- Homes
- 399
- Sold or booked
- 0%
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of SHREEPATI BAYVIEW, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GIRGAON EKTA SOCIETY | 0% | 0% | 0% | 0% |
| WING B | 0% | 0% | 0% | 0% |
| WING C | 0% | 0% | 0% | 0% |
| WING D | 0% | 0% | 0% | 0% |
| WING E | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREEPATI BAYVIEW every month.
SHREEPATI BAYVIEW: buildings, flats and land, as filed on MahaRERA
- Buildings: GIRGAON EKTA SOCIETY (24 floors) · WING B (20 floors) · WING C (24 floors) · WING D (23 floors) · WING E (24 floors)
- Land: 6,583 sq m (about 1.6 acres) · sanctioned built-up 10,437 sq m · recreational space 415 sq m
- Boundaries filed include: JAGANNATH SHANKAR SETH ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shreepati Build Infra Investment (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 2 past the promised date (typically 42 months late); 2 lapsed. 10 complaints on MahaRERA across 4 projects.
Read Google reviews of SHREEPATI BAYVIEW →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREEPATI BAYVIEW: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREEPATI BAYVIEW
What is the possession date of SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREEPATI BAYVIEW in Nana Chowk, Mumbai is 30 December 2026.
Is the builder's possession date different from the MahaRERA date for SHREEPATI BAYVIEW?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREEPATI BAYVIEW's builder has filed on MahaRERA, the official one, is 30 December 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREEPATI BAYVIEW in Nana Chowk, Mumbai is P51900010019.
Is SHREEPATI BAYVIEW registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW is registered as P51900010019 and its status is "De-Registered". On MahaRERA's own list: Deregistered by MahaRERA. MahaRERA has deregistered this project by order. Builders often apply for this themselves when a project doesn't go ahead -- read the order before paying anything.
What is the construction status of SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW's status on MahaRERA is "De-Registered". As filed by the builder, slab work is 0% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does SHREEPATI BAYVIEW have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHREEPATI BAYVIEW safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW is registered on MahaRERA as P51900010019, its MahaRERA status is "De-Registered", its completion date has not been moved by the builder, 1 complaint is listed against it and it is on MahaRERA's list "Deregistered by MahaRERA". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREEPATI BAYVIEW's possession date changes?
The latest dates are on SHREEPATI BAYVIEW's MahaRERA page (P51900010019). GharKundli's Kundli Watch sends a free WhatsApp update on SHREEPATI BAYVIEW every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREEPATI BAYVIEW have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW has 5 buildings filed: GIRGAON EKTA SOCIETY with 24 floors; WING B with 20 floors; WING C with 24 floors; WING D with 23 floors; WING E with 24 floors.
How big is the land of SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW stands on 6,583 sq m of land (about 1.6 acres), with 10,437 sq m of sanctioned built-up area and 415 sq m of recreational open space.
What is the track record of SHREEPATI BAYVIEW's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shreepati Build Infra Investment (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 2 past the promised date (typically 42 months late); 2 lapsed. 10 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHREEPATI BAYVIEW?
Google Maps has reviews of SHREEPATI BAYVIEW written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREEPATI BAYVIEW?
SHREEPATI BAYVIEW by SHREEPATI BUILD INFRA INVESTMENT LIMITED is in Nana Chowk, Mumbai (pincode 400004), near Girgaon, Khetwadi, Grant Road, Maharashtra, and is registered on MahaRERA as P51900010019, per GharKundli's check of MahaRERA records. Its boundaries filed there include JAGANNATH SHANKAR SETH ROAD.
How many homes are in SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW has 399 homes in 5 towers registered on MahaRERA, and 0% of them are sold or booked.
When was SHREEPATI BAYVIEW registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREEPATI BAYVIEW was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREEPATI BAYVIEW?
3 court cases are listed for SHREEPATI BAYVIEW on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHREEPATI BAYVIEW?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREEPATI BUILD INFRA INVESTMENT LIMITED, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHREEPATI BAYVIEW
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
All projects in Girgaon (400004) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.