PRINCE TOWER

by Punith Buildtech Private Limited · Dharavi, MumbaiAlso near Matunga, Sion West, Mahim

Possession date of PRINCE TOWER: 30 June 2025, moved from 30 December 2022 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900006933. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about PRINCE TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PRINCE TOWER has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900011648)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-06-2025”

Source: PRINCE TOWER’s extension records on MahaRERA (P51900006933), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PRINCE TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900006933
Status
Lapsed (registration period ended)
Builder
Punith Buildtech Private Limited
Location
Dharavi, Mumbai · 400017
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
December 2022
Latest completion date
June 2025
Delay so far
30 months
Homes
101
Sold or booked
76%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of PRINCE TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PRINCE TOWER100%100%100%98%

Commencement certificate (CC), as filed on MahaRERA

  • PRINCE TOWER: covers ground +19 upper floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRINCE TOWER every month.

PRINCE TOWER: buildings, flats and land, as filed on MahaRERA

  • Buildings: PRINCE TOWER (25 floors, 101 units)
  • Land: 2,324 sq m (about 0.6 acres) · sanctioned built-up 2,058 sq m · recreational space 165 sq m
  • Boundaries filed include: 30 FEET LAYOUT ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PRINCE TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PRINCE TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PRINCE TOWER

What is the possession date of PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRINCE TOWER in Dharavi, Mumbai is 30 June 2025 — 30 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PRINCE TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PRINCE TOWER's builder has filed on MahaRERA, the official one, is 30 June 2025, already 30 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PRINCE TOWER extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER's builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-06-2025".

What is the RERA number of PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PRINCE TOWER in Dharavi, Mumbai is P51900006933.

Is PRINCE TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER is registered as P51900006933 and its status is "Lapsed (registration period ended)".

What is the construction status of PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PRINCE TOWER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does PRINCE TOWER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PRINCE TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER is registered on MahaRERA as P51900006933, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PRINCE TOWER's possession date changes?

The latest dates are on PRINCE TOWER's MahaRERA page (P51900006933). GharKundli's Kundli Watch sends a free WhatsApp update on PRINCE TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PRINCE TOWER have?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER has one building filed: PRINCE TOWER with 25 floors and 101 units.

How big is the land of PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER stands on 2,324 sq m of land (about 0.6 acres), with 2,058 sq m of sanctioned built-up area and 165 sq m of recreational open space.

Where can I read reviews of PRINCE TOWER?

Google Maps has reviews of PRINCE TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PRINCE TOWER?

PRINCE TOWER by Punith Buildtech Private Limited is in Dharavi, Mumbai (pincode 400017), near Matunga, Sion West, Mahim, Maharashtra, and is registered on MahaRERA as P51900006933, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30 FEET LAYOUT ROAD.

How many homes are in PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER has 101 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.

When was PRINCE TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRINCE TOWER was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PRINCE TOWER?

No court cases are listed for PRINCE TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PRINCE TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Punith Buildtech Private Limited.

Other projects in pincode 400017

All 9 projects in Dharavi (400017) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.