Skip to content
GharKundli

SKY IMPERIA

by SKYLINE STAR CONSTRUCTIONS LLP · Vile Parle East, MumbaiAlso near Vileeparle East, Vileparle West, Sahar P and T Colony

Registered on MahaRERA under P51800047121. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on SKY IMPERIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800047121
Status
Completed
Builder
SKYLINE STAR CONSTRUCTIONS LLP
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
10 Oct 2022
Completion date at registration
December 2025
Homes
28
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

SKY IMPERIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SKY IMPERIA

Is SKY IMPERIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SKY IMPERIA is registered as P51800047121 and its status is "Completed".

Where is SKY IMPERIA?

SKY IMPERIA by SKYLINE STAR CONSTRUCTIONS LLP is in Vile Parle East, Mumbai (pincode 400057), near Vileeparle East, Vileparle West, Sahar P and T Colony, Maharashtra, and is registered on MahaRERA as P51800047121, per GharKundli's check of MahaRERA records.

When is possession of SKY IMPERIA due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SKY IMPERIA in Vile Parle East, Mumbai is 31 December 2025.

Does SKY IMPERIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in SKY IMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), SKY IMPERIA has 28 homes in 1 tower registered on MahaRERA.

When was SKY IMPERIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SKY IMPERIA was registered on MahaRERA on 10 October 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SKY IMPERIA?

No court cases are listed for SKY IMPERIA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SKY IMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SKYLINE STAR CONSTRUCTIONS LLP.

Other projects in pincode 400057