Shubhada Co-operative Housing Society Ltd.

by BHOOMIVIJAY PROPERTIES PRIVATE LIMITED · Ville parle, MumbaiAlso near Vile Parle East, Andheri East, Vile Parle West

Possession date of Shubhada Co-operative Housing Society Ltd.: 30 June 2027, moved from 30 June 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800001693, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Shubhada Co-operative Housing Society Ltd.?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shubhada Co-operative Housing Society Ltd. has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800008431)

    Reason the builder gave MahaRERA:
    “The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc due to the pandemic. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Als…” Read the full reason“The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc due to the pandemic. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. Also, we had to halt our construction recently as a few…”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013335)

    Reason the builder gave MahaRERA:
    “We had applied for approval of Plans for 7 Floors of Wing A, B and C. The same got approved upto 3rd Floors for Wing A and C and Upto 4th Floor for wing B. So far we have completed 50% of slab structure and awaiting for further C.C. We had…” Read the full reason“We had applied for approval of Plans for 7 Floors of Wing A, B and C. The same got approved upto 3rd Floors for Wing A and C and Upto 4th Floor for wing B. So far we have completed 50% of slab structure and awaiting for further C.C. We had applied for further CC with reference to approved plan dated 22-11-2018. But the same got delayed due to ambiguity in DCR Rules and payment schemes. There were amendments in DCR Rules which lead to delay in various project approvals and hence the under- Construction project got delayed. In the year 2020, lockdown restrictions had disrupted the supply chai…”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800018354)

    Reason the builder gave MahaRERA:
    “Project got delayed in the first half of year 2023 due to critical shortages of key materials like sand and ready-mix concrete, causing delays in construction schedules. In third quarter 2023, implementation of stringent state regulations,…” Read the full reason“Project got delayed in the first half of year 2023 due to critical shortages of key materials like sand and ready-mix concrete, causing delays in construction schedules. In third quarter 2023, implementation of stringent state regulations, particularly stricter air pollution control measures for developers significantly impeded procuring construction materials and managing debris disposal.”
  5. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT51800025281)

    Reason the builder gave MahaRERA:
    “The primary reason for extension request is that particular flat belongs to an original member who has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The delay in execution of the PAAA is due to disputes among the…” Read the full reason“The primary reason for extension request is that particular flat belongs to an original member who has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The delay in execution of the PAAA is due to disputes among the original flat members, which is beyond the control of the developer. To address this situation, we submitted a Registered Undertaking in favor of the Deputy Chief Engineer of Brihanmumbai Mahanagar Palika (BMC), stating that we will not hand over possession of this flat until the original member signs and executes the PAAA and a copy of the registered PAA…”
  6. 30 June 2027

    Extended at the builder's request (MahaRERA application EA22072621835)

    Reason the builder gave MahaRERA:
    “We declare that, the construction of the project has been completed in all respects, and the project is 100% physically completed. An Occupancy Certificate (OC) has been obtained for the entire project, except one unit - Flat No. 309, situa…” Read the full reason“We declare that, the construction of the project has been completed in all respects, and the project is 100% physically completed. An Occupancy Certificate (OC) has been obtained for the entire project, except one unit - Flat No. 309, situated on the 3rd Floor of Wing C. The original member belongs to old Flat number C-35 & New Flat No C-309, despite of repeated request & reminders over the period of years has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The execution of the PAAA has been delayed due to disputes amongst the original members of the society, which…”

Source: Shubhada Co-operative Housing Society Ltd.’s extension records on MahaRERA (P51800001693), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shubhada Co-operative Housing Society Ltd.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001693
Status
Registered and active
Builder
BHOOMIVIJAY PROPERTIES PRIVATE LIMITED
Location
Ville parle, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
29 Jul 2017
Completion date at registration
June 2021
Latest completion date
June 2027
Delay so far
72 months
Homes
43
Sold or booked
100%
Towers
3
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found

Construction progress of Shubhada Co-operative Housing Society Ltd., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shubhada Wing - A100%100%100%100%
Shubhada Wing - B100%100%100%100%
Shubhada Wing - C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Shubhada Wing - A: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubhada Co-operative Housing Society Ltd. every month.

Shubhada Co-operative Housing Society Ltd.: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK969 – 1,27637
2 BHK640 – 7586
  • Buildings: Shubhada Wing - A (10 floors, 11 units) · Shubhada Wing - B (10 floors, 20 units) · Shubhada Wing - C (10 floors, 12 units)
  • Car parking: 98 covered, 8 open
  • Land: 2,975 sq m (about 0.7 acres) · sanctioned built-up 3,375 sq m · recreational space 585 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shubhada Co-operative Housing Society Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shubhada Co-operative Housing Society Ltd.: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shubhada Co-operative Housing Society Ltd.

What is the possession date of Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shubhada Co-operative Housing Society Ltd. in Ville parle, Mumbai is 30 June 2027 — 72 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Shubhada Co-operative Housing Society Ltd.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubhada Co-operative Housing Society Ltd.'s builder has filed on MahaRERA, the official one, is 30 June 2027, already 72 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shubhada Co-operative Housing Society Ltd. extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd.'s builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2022, giving the reason "The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc due to the pandemic. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. Also, we had to halt our construction recently as a few…"; to 31 December 2023, giving the reason "We had applied for approval of Plans for 7 Floors of Wing A, B and C. The same got approved upto 3rd Floors for Wing A and C and Upto 4th Floor for wing B. So far we have completed 50% of slab structure and awaiting for further C.C. We had applied for further CC with reference to approved plan dated 22-11-2018. But the same got delayed due to ambiguity in DCR Rules and payment schemes. There were amendments in DCR Rules which lead to delay in various project approvals and hence the under- Construction project got delayed. In the year 2020, lockdown restrictions had disrupted the supply chai…"; to 30 June 2024, giving the reason "Project got delayed in the first half of year 2023 due to critical shortages of key materials like sand and ready-mix concrete, causing delays in construction schedules. In third quarter 2023, implementation of stringent state regulations, particularly stricter air pollution control measures for developers significantly impeded procuring construction materials and managing debris disposal."; to 30 June 2026, giving the reason "The primary reason for extension request is that particular flat belongs to an original member who has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The delay in execution of the PAAA is due to disputes among the original flat members, which is beyond the control of the developer. To address this situation, we submitted a Registered Undertaking in favor of the Deputy Chief Engineer of Brihanmumbai Mahanagar Palika (BMC), stating that we will not hand over possession of this flat until the original member signs and executes the PAAA and a copy of the registered PAA…"; to 30 June 2027, giving the reason "We declare that, the construction of the project has been completed in all respects, and the project is 100% physically completed. An Occupancy Certificate (OC) has been obtained for the entire project, except one unit - Flat No. 309, situated on the 3rd Floor of Wing C. The original member belongs to old Flat number C-35 & New Flat No C-309, despite of repeated request & reminders over the period of years has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The execution of the PAAA has been delayed due to disputes amongst the original members of the society, which…".

What is the RERA number of Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shubhada Co-operative Housing Society Ltd. in Ville parle, Mumbai is P51800001693.

Is Shubhada Co-operative Housing Society Ltd. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. is registered as P51800001693 and its status is "Registered and active".

What is the construction status of Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Shubhada Co-operative Housing Society Ltd. have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Shubhada Co-operative Housing Society Ltd. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. is registered on MahaRERA as P51800001693, its completion date has moved 72 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shubhada Co-operative Housing Society Ltd.'s possession date changes?

The latest dates are on Shubhada Co-operative Housing Society Ltd.'s MahaRERA page (P51800001693). GharKundli's Kundli Watch sends a free WhatsApp update on Shubhada Co-operative Housing Society Ltd. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shubhada Co-operative Housing Society Ltd. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. has 3 buildings filed: Shubhada Wing - A with 10 floors and 11 units; Shubhada Wing - B with 10 floors and 20 units; Shubhada Wing - C with 10 floors and 12 units.

What are the flat sizes (carpet area) in Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shubhada Co-operative Housing Society Ltd.: 3 BHK: 969 to 1276 sq ft carpet (37 homes); 2 BHK: 640 to 758 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shubhada Co-operative Housing Society Ltd. have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 98 covered and 8 open car parking spaces for Shubhada Co-operative Housing Society Ltd..

How big is the land of Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. stands on 2,975 sq m of land (about 0.7 acres), with 3,375 sq m of sanctioned built-up area and 585 sq m of recreational open space.

Where can I read reviews of Shubhada Co-operative Housing Society Ltd.?

Google Maps has reviews of Shubhada Co-operative Housing Society Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shubhada Co-operative Housing Society Ltd.?

Shubhada Co-operative Housing Society Ltd. by BHOOMIVIJAY PROPERTIES PRIVATE LIMITED is in Ville parle, Mumbai (pincode 400057), near Vile Parle East, Andheri East, Vile Parle West, Maharashtra, and is registered on MahaRERA as P51800001693, per GharKundli's check of MahaRERA records.

How many homes are in Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. has 43 homes in 3 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Shubhada Co-operative Housing Society Ltd. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shubhada Co-operative Housing Society Ltd. was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Shubhada Co-operative Housing Society Ltd.?

1 court case is listed for Shubhada Co-operative Housing Society Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Shubhada Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BHOOMIVIJAY PROPERTIES PRIVATE LIMITED.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400057

All 250 projects in Vile Parle East (400057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.