GharKundli

Neumec godawari

by NEUMEC ESTATE DEVELOPER LLP · Vile Parle, MumbaiAlso near Vileparle East, Santacruz West, Andheri East

Possession date of Neumec godawari: 31 December 2026, moved from 31 March 2019 (93 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005145, and currently active. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Neumec godawari?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Neumec godawari has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT51800002045)

    Reason the builder gave MahaRERA: “DELAY IN GETTING HEIGHT APPROVAL AND GETTING BUILDING PLAN APPROVAL DUE TO IMPLEMENTATION OF NEW DP”
  3. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT51800011055)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800024545)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have received Part OC for our project, the OC is pending for only 14th floor, the consent of which has been taken for extension.”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EA09092622496)

    Reason the builder gave MahaRERA:
    “The project has been delayed as the Part Occupation Certificate for the completed portions has been received, while the balance certificate is pending due to remaining finishing, development work, and approval-related issues. Necessary effo…” Read the full reason“The project has been delayed as the Part Occupation Certificate for the completed portions has been received, while the balance certificate is pending due to remaining finishing, development work, and approval-related issues. Necessary efforts are being made to complete the pending work and obtain the required approvals at the earliest. We kindly request an extension up to 31-12-2026 to.”

Source: Neumec godawari’s extension records on MahaRERA (P51800005145), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Neumec godawari

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005145
Status
Registered and active
Builder
NEUMEC ESTATE DEVELOPER LLP
Location
Vile Parle, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
March 2019
Latest completion date
December 2026
Delay so far
93 months
Homes
19
Sold or booked
100%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Neumec godawari, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NEUMEC GODAWARI100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • NEUMEC GODAWARI: covers 15 (Stilt + 14 Upper floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neumec godawari every month.

Neumec godawari: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK413 – 41510
3 BHK9675
2 BHK567 – 8354

The builder’s record and reviews

Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 6 past the promised date (typically 40 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects.

Read Google reviews of Neumec godawari →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Neumec godawari: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Neumec godawari

What is the possession date of Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neumec godawari in Vile Parle, Mumbai is 31 December 2026 — 93 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Neumec godawari?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Neumec godawari's builder has filed on MahaRERA, the official one, is 31 December 2026, already 93 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Neumec godawari extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2020, giving the reason "DELAY IN GETTING HEIGHT APPROVAL AND GETTING BUILDING PLAN APPROVAL DUE TO IMPLEMENTATION OF NEW DP"; to 30 September 2022, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19."; to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have received Part OC for our project, the OC is pending for only 14th floor, the consent of which has been taken for extension."; to 31 December 2026, giving the reason "The project has been delayed as the Part Occupation Certificate for the completed portions has been received, while the balance certificate is pending due to remaining finishing, development work, and approval-related issues. Necessary efforts are being made to complete the pending work and obtain the required approvals at the earliest. We kindly request an extension up to 31-12-2026 to.".

What is the RERA number of Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neumec godawari in Vile Parle, Mumbai is P51800005145.

Is Neumec godawari registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari is registered as P51800005145 and its status is "Registered and active".

What is the construction status of Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NEUMEC GODAWARI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Neumec godawari have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Neumec godawari safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari is registered on MahaRERA as P51800005145, its completion date has moved 93 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Neumec godawari's possession date changes?

The latest dates are on Neumec godawari's MahaRERA page (P51800005145). GharKundli's Kundli Watch sends a free WhatsApp update on Neumec godawari every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Neumec godawari have?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari has one building filed: NEUMEC GODAWARI with 15 floors and 19 units.

What are the flat sizes (carpet area) in Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Neumec godawari: 1 BHK: 413 to 415 sq ft carpet (10 homes); 3 BHK: 967 sq ft carpet (5 homes); 2 BHK: 567 to 835 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Neumec godawari have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Neumec godawari.

How big is the land of Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari stands on 434 sq m of land (about 0.1 acres), with 1,285 sq m of sanctioned built-up area.

What is the track record of Neumec godawari's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 6 past the promised date (typically 40 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Neumec godawari?

Google Maps has reviews of Neumec godawari written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Neumec godawari?

Neumec godawari by NEUMEC ESTATE DEVELOPER LLP is in Vile Parle, Mumbai (pincode 400057), near Vileparle East, Santacruz West, Andheri East, Maharashtra, and is registered on MahaRERA as P51800005145, per GharKundli's check of MahaRERA records.

How many homes are in Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari has 19 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Neumec godawari registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec godawari was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Neumec godawari?

No court cases are listed for Neumec godawari on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Neumec godawari?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEUMEC ESTATE DEVELOPER LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400057

All 250 projects in Vile Parle East (400057) →

Other projects by NEUMEC ESTATE DEVELOPER LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.