ANURADHA TOWER
by Dinesh Shivajirao Ghadage · Nerul, MumbaiAlso near Sion, Kalanagar, Bandra East, Dharavi
Possession: ANURADHA TOWER is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900005892. Status: Completed. 20 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ANURADHA TOWER?
How the possession date of ANURADHA TOWER has moved
31 December 2018
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT51900006359)
Reason the builder gave MahaRERA: “Time extension due to OC have been already filed in RERA court.OC documents have been submitted in MHADA ON 27/11/2018. Due to change in authority from BMC to MHADA has caused delay.”
31 July 2021
Extended at the builder's request (MahaRERA application EXT51900008940)
Reason the builder gave MahaRERA: “I HAVE OBTAINED FURTHER COMMENCEMENT CERTIFICATE FOR THE PROJECT WHICH HAS BEEN UPLOADED HEREWITH.”
31 December 2022
Extended at the builder's request (MahaRERA application EXT51900010177)
Reason the builder gave MahaRERA: “Part Occupation up to 7th floor have been obtained from MH and AD board. Require RERA extension for 8th floor OC.”
Source: ANURADHA TOWER’s extension records on MahaRERA (P51900005892), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANURADHA TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 20 complaints and 4 court cases, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900005892
- Status
- Completed
- Builder
- Dinesh Shivajirao Ghadage
- Location
- Nerul, Mumbai · 400031
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2022
- Delay so far
- 48 months
- Homes
- 33
- Towers
- 1
- Complaints on MahaRERA
- 20
- Court cases listed
- 4
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of ANURADHA TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANURADHA TOWER | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANURADHA TOWER every month.
ANURADHA TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: ANURADHA TOWER (13 floors)
- Land: 440 sq m (about 0.1 acres) · sanctioned built-up 1,172 sq m · recreational space 415 sq m
- Boundaries filed include: 12 MTS ROAD, 18 MTS ROAD, MAHADA COLONY
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ANURADHA TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANURADHA TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANURADHA TOWER
What is the possession date of ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ANURADHA TOWER in Nerul, Mumbai is 31 December 2022 — 48 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ANURADHA TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANURADHA TOWER's builder has filed on MahaRERA, the official one, is 31 December 2022, already 48 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANURADHA TOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2020, giving the reason "Time extension due to OC have been already filed in RERA court.OC documents have been submitted in MHADA ON 27/11/2018. Due to change in authority from BMC to MHADA has caused delay."; to 31 July 2021, giving the reason "I HAVE OBTAINED FURTHER COMMENCEMENT CERTIFICATE FOR THE PROJECT WHICH HAS BEEN UPLOADED HEREWITH."; to 31 December 2022, giving the reason "Part Occupation up to 7th floor have been obtained from MH and AD board. Require RERA extension for 8th floor OC.".
What is the RERA number of ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ANURADHA TOWER in Nerul, Mumbai is P51900005892.
Is ANURADHA TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER is registered as P51900005892 and its status is "Completed".
What is the construction status of ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER's status on MahaRERA is "Completed". As filed by the builder, slab work on ANURADHA TOWER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ANURADHA TOWER have complaints on MahaRERA?
20 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANURADHA TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER is registered on MahaRERA as P51900005892, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 20 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANURADHA TOWER's possession date changes?
The latest dates are on ANURADHA TOWER's MahaRERA page (P51900005892). GharKundli's Kundli Watch sends a free WhatsApp update on ANURADHA TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANURADHA TOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER has one building filed: ANURADHA TOWER with 13 floors.
How big is the land of ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER stands on 440 sq m of land (about 0.1 acres), with 1,172 sq m of sanctioned built-up area and 415 sq m of recreational open space.
Where can I read reviews of ANURADHA TOWER?
Google Maps has reviews of ANURADHA TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 20 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANURADHA TOWER?
ANURADHA TOWER by Dinesh Shivajirao Ghadage is in Nerul, Mumbai (pincode 400031), near Sion, Kalanagar, Bandra East, Dharavi, Maharashtra, and is registered on MahaRERA as P51900005892, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTS ROAD, 18 MTS ROAD, MAHADA COLONY.
How many homes are in ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER has 33 homes in 1 tower registered on MahaRERA.
When was ANURADHA TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ANURADHA TOWER was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ANURADHA TOWER?
4 court cases are listed for ANURADHA TOWER on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ANURADHA TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dinesh Shivajirao Ghadage.
Check it yourself on MahaRERA
- How to check the possession date of ANURADHA TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nerul
- PLATINUM ELYSIUM
- DRISHTANT CO-OPERATIVE HOUSING SOCIETY LIMITED
- ANAND VAIBHAV CHSL
- OMKAR PLANET
- NOVA ARK
- NOVA VISTA
- LA VESTA
- DDSR DREAMWOOD CHS LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.