by SAHAJ DEVELOPERS · Parel, MumbaiAlso near Matunga, Wadala West, Dadar East

Possession date of 759: 30 September 2025, moved from 31 October 2019 (71 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900004050. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2025) has passed.

What do you want to know about 759?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on 759

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the September 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900004050
Status
Lapsed (registration period ended)
Builder
SAHAJ DEVELOPERS
Location
Parel, Mumbai · 400014
Project type
Residential / Group Housing
Registered on
7 Aug 2017
Completion date at registration
October 2019
Latest completion date
September 2025
Delay so far
71 months
Homes
29
Sold or booked
100%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of 759, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
759100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • 759: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 759 every month.

759: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,128 – 1,30319
2 BHK795 – 7966
Other1,9142
4 BHK1,2741
5 BHK1,6951

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 759 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

759: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 759

What is the possession date of 759?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 759 in Parel, Mumbai is 30 September 2025 — 71 months later than 31 October 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for 759?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 759's builder has filed on MahaRERA, the official one, is 30 September 2025, already 71 months later than the 31 October 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of 759?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 759 in Parel, Mumbai is P51900004050.

Is 759 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 is registered as P51900004050 and its status is "Lapsed (registration period ended)".

What is the construction status of 759?

According to GharKundli's check of MahaRERA records (updated October 2026), 759's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on 759 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does 759 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 759 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 is registered on MahaRERA as P51900004050, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 71 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 759's possession date changes?

The latest dates are on 759's MahaRERA page (P51900004050). GharKundli's Kundli Watch sends a free WhatsApp update on 759 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 759 have?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 has one building filed: 759 with 28 floors and 29 units.

What are the flat sizes (carpet area) in 759?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 759: 3 BHK: 1128 to 1303 sq ft carpet (19 homes); 2 BHK: 795 to 796 sq ft carpet (6 homes); Other: 1914 sq ft carpet (2 homes); 4 BHK: 1274 sq ft carpet (1 homes); 5 BHK: 1695 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of 759?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 stands on 899 sq m of land (about 0.2 acres), with 2,696 sq m of sanctioned built-up area.

Where can I read reviews of 759?

Google Maps has reviews of 759 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 759?

759 by SAHAJ DEVELOPERS is in Parel, Mumbai (pincode 400014), near Matunga, Wadala West, Dadar East, Maharashtra, and is registered on MahaRERA as P51900004050, per GharKundli's check of MahaRERA records. Its boundaries filed there include JAHANGIR VIMA DALAL ROAD.

How many homes are in 759?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 has 29 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was 759 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 759 was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 759?

No court cases are listed for 759 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of 759?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAHAJ DEVELOPERS.