Aangan
by Indus Valley Constructions LLP · Matunga West, MumbaiAlso near Dadar West, Mahim, Shivaji Park
Possession: Aangan is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900015218. Status: Completed. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Aangan?
How the possession date of Aangan has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51900018123)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”30 April 2025
Extended at the builder's request (MahaRERA application EXT51900025806)
Reason the builder gave MahaRERA:
“We, M/s. Indus Valley Constructions LLP, hereby declare the following with respect to the project Aangan bearing registration number. P51900015218 registered under MahaRERA. The delay in the completion of the real estate project has been pr…” Read the full reason
“We, M/s. Indus Valley Constructions LLP, hereby declare the following with respect to the project Aangan bearing registration number. P51900015218 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 30th April 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensu…”
Source: Aangan’s extension records on MahaRERA (P51900015218), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aangan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 2 court cases, and how it ended
- Construction pace against the April 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900015218
- Status
- Completed
- Builder
- Indus Valley Constructions LLP
- Location
- Matunga West, Mumbai · 400016
- Project type
- Residential / Group Housing
- Registered on
- 8 Feb 2018
- Completion date at registration
- December 2023
- Latest completion date
- April 2025
- Delay so far
- 16 months
- Homes
- 128
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 2
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Aangan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aangan B Wing | 100% | 100% | 100% | 75% |
| Aangan A Wing | 100% | 100% | 100% | 75% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aangan every month.
Aangan: buildings, flats and land, as filed on MahaRERA
- Buildings: Aangan B Wing (40 floors) · Aangan A Wing (23 floors)
- Land: 1,421 sq m (about 0.4 acres) · sanctioned built-up 7,328 sq m
- Boundaries filed include: T H Kataria Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Indus Valley Constructions (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months). 5 complaints on MahaRERA across 2 projects.
Read Google reviews of Aangan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aangan: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aangan
What is the possession date of Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aangan in Matunga West, Mumbai is 30 April 2025 — 16 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Aangan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aangan's builder has filed on MahaRERA, the official one, is 30 April 2025, already 16 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aangan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 April 2025, giving the reason "We, M/s. Indus Valley Constructions LLP, hereby declare the following with respect to the project Aangan bearing registration number. P51900015218 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 30th April 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensu…".
What is the RERA number of Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aangan in Matunga West, Mumbai is P51900015218.
Is Aangan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan is registered as P51900015218 and its status is "Completed".
What is the construction status of Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Aangan have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Aangan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan is registered on MahaRERA as P51900015218, its MahaRERA status is "Completed", its completion date has moved 16 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Aangan's possession date changes?
The latest dates are on Aangan's MahaRERA page (P51900015218). GharKundli's Kundli Watch sends a free WhatsApp update on Aangan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aangan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan has 2 buildings filed: Aangan B Wing with 40 floors; Aangan A Wing with 23 floors.
How big is the land of Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan stands on 1,421 sq m of land (about 0.4 acres), with 7,328 sq m of sanctioned built-up area.
What is the track record of Aangan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Indus Valley Constructions (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months). 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Aangan?
Google Maps has reviews of Aangan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aangan?
Aangan by Indus Valley Constructions LLP is in Matunga West, Mumbai (pincode 400016), near Dadar West, Mahim, Shivaji Park, Maharashtra, and is registered on MahaRERA as P51900015218, per GharKundli's check of MahaRERA records. Its boundaries filed there include T H Kataria Road.
How many homes are in Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan has 128 homes in 2 towers registered on MahaRERA.
When was Aangan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aangan was registered on MahaRERA on 8 February 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Aangan?
2 court cases are listed for Aangan on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Indus Valley Constructions LLP.
Check it yourself on MahaRERA
- How to check the possession date of Aangan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Matunga West
All 83 projects in Mahim (400016) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.