BELLAGIO
by ESTELLE ESTATES & INFRASTRUCTURE PRIVATE LIMITED (Living) · Byculla, MumbaiAlso near Nagpada, Agripada, mumbai central
Possession date of BELLAGIO: 31 July 2026, moved from 30 December 2023 (27 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900016554. Status: Lapsed (registration period ended). Its completion date has moved from December 2023 to July 2026: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about BELLAGIO?
How the possession date of BELLAGIO has moved
30 December 2023
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51900019021)
Reason the builder gave MahaRERA:
“We have submitted an application (RERA Number P51900016554) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7/31 of the RERA Act, requesting an extension for a duration of 31-03-20…” Read the full reason
“We have submitted an application (RERA Number P51900016554) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7/31 of the RERA Act, requesting an extension for a duration of 31-03-2026 months. The project has encountered several challenges that have necessitated a revision of our original timeline This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project Section 7(3) of the RERA Act has giv…”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BELLAGIO’s extension records on MahaRERA (P51900016554), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BELLAGIO
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900016554
- Status
- Lapsed (registration period ended)
- Builder
- ESTELLE ESTATES & INFRASTRUCTURE PRIVATE LIMITED
- Location
- Byculla, Mumbai · 400008
- Project type
- Residential / Group Housing
- Registered on
- 23 May 2018
- Completion date at registration
- December 2023
- Latest completion date
- July 2026
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 79
- Sold or booked
- 41%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BELLAGIO, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BELLAGIO | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BELLAGIO: covers This C.C. is granted upto a plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BELLAGIO every month.
BELLAGIO: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 405 – 1,167 | 52 |
| Shops | 54 – 1,000 | 29 |
| 1 BHK | 405 – 567 | 25 |
| 4 BHK | 1,452 | 1 |
- Buildings: BELLAGIO (26 floors, 107 units)
- Land: 1,383 sq m (about 0.3 acres) · sanctioned built-up 5,860 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects.
Read Google reviews of BELLAGIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BELLAGIO: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BELLAGIO
What is the possession date of BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BELLAGIO in Byculla, Mumbai is 31 July 2026 — 27 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for BELLAGIO?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BELLAGIO's builder has filed on MahaRERA, the official one, is 31 July 2026, already 27 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BELLAGIO extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "We have submitted an application (RERA Number P51900016554) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7/31 of the RERA Act, requesting an extension for a duration of 31-03-2026 months. The project has encountered several challenges that have necessitated a revision of our original timeline This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project Section 7(3) of the RERA Act has giv…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BELLAGIO in Byculla, Mumbai is P51900016554.
Is BELLAGIO registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO is registered as P51900016554 and its status is "Lapsed (registration period ended)".
What is the construction status of BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BELLAGIO is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BELLAGIO have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BELLAGIO safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO is registered on MahaRERA as P51900016554, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BELLAGIO's possession date changes?
The latest dates are on BELLAGIO's MahaRERA page (P51900016554). GharKundli's Kundli Watch sends a free WhatsApp update on BELLAGIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BELLAGIO have?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO has one building filed: BELLAGIO with 26 floors and 107 units.
What are the flat sizes (carpet area) in BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for BELLAGIO: 2 BHK: 405 to 1167 sq ft carpet (52 homes); 1 BHK: 405 to 567 sq ft carpet (25 homes); 4 BHK: 1452 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO stands on 1,383 sq m of land (about 0.3 acres), with 5,860 sq m of sanctioned built-up area.
What is the track record of BELLAGIO's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Living Stone Construction (a group of 7 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 67 months); 3 still being built, 2 past the promised date (typically 12 months late); 3 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BELLAGIO?
Google Maps has reviews of BELLAGIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BELLAGIO?
BELLAGIO by ESTELLE ESTATES & INFRASTRUCTURE PRIVATE LIMITED (Living) is in Byculla, Mumbai (pincode 400008), near Nagpada, Agripada, mumbai central, Maharashtra, and is registered on MahaRERA as P51900016554, per GharKundli's check of MahaRERA records.
How many homes are in BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO has 79 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.
When was BELLAGIO registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BELLAGIO was registered on MahaRERA on 23 May 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on BELLAGIO?
No court cases are listed for BELLAGIO on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of BELLAGIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ESTELLE ESTATES & INFRASTRUCTURE PRIVATE LIMITED, the company Living files this project under.
Check it yourself on MahaRERA
- How to check the possession date of BELLAGIO
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Byculla
- 11 ASTORIA
- ARIHANT HEIGHTS - JARIWALA AND KADUSKAR
- VIDA CREST
- VIVA
- LAKADAWALA HEIGHTS
- ICON BY MERX
- PRESTIGE JASDAN CLASSIC
- MONTESOUTH PILATUS 4
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.