by HANWARE REALTY · Dharavi, MumbaiAlso near Matunga, Sion West, Mahim

Possession date of HANWARE HEIGHTS: 31 December 2024, moved from 30 June 2021 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900019260. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about HANWARE HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HANWARE HEIGHTS has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51900009659)

    Reason the builder gave MahaRERA:
    “REASON FOR DELAY ARE 1) COVID-19 LOCKDOWN 2) SHORTAGE OF LABOUR DUE TO MIGRATION OF LABOURS TO THEIR NATIVE PLACES. 3) SHORTAGE OF CONSTRUCTION MATERIALS DUE TO COVID-19 LOCKDOWN 4) INCREASED COVID-19 CASES IN DHARAVI WHERE OUR PROJECT IS S…” Read the full reason“REASON FOR DELAY ARE 1) COVID-19 LOCKDOWN 2) SHORTAGE OF LABOUR DUE TO MIGRATION OF LABOURS TO THEIR NATIVE PLACES. 3) SHORTAGE OF CONSTRUCTION MATERIALS DUE TO COVID-19 LOCKDOWN 4) INCREASED COVID-19 CASES IN DHARAVI WHERE OUR PROJECT IS SITUATED.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51900012169)

    Reason the builder gave MahaRERA: “SHORTAGE OF LABOURS AND BUILDING MATERIALS DUE TO COVID 19”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51900016894)

    Reason the builder gave MahaRERA:
    “Construction work is stopped in the Covid 19 period due to the increased cases in Dharavi area where project is situated. After that construction work got slow for few months due to migration of labours in their villages because of Covid 19…” Read the full reason“Construction work is stopped in the Covid 19 period due to the increased cases in Dharavi area where project is situated. After that construction work got slow for few months due to migration of labours in their villages because of Covid 19 lockdown. The our allottees are aware of all our problems and they are co-operating with us and have given their consents for extension. We request the authority to please give us further extension to complete the project.”

Source: HANWARE HEIGHTS’s extension records on MahaRERA (P51900019260), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HANWARE HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 7 court cases, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900019260
Status
Lapsed (registration period ended)
Builder
HANWARE REALTY
Location
Dharavi, Mumbai · 400017
Project type
Others
Registered on
14 Jan 2019
Completion date at registration
June 2021
Latest completion date
December 2024
Delay so far
42 months
Homes
112
Towers
1
Complaints on MahaRERA
2
Court cases listed
7
Title report on file
Not found

Construction progress of HANWARE HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HANWARE HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HANWARE HEIGHTS every month.

HANWARE HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Hanware Realty (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 7 months). 2 complaints on MahaRERA across 1 project.

Read Google reviews of HANWARE HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HANWARE HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HANWARE HEIGHTS

What is the possession date of HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HANWARE HEIGHTS in Dharavi, Mumbai is 31 December 2024 — 42 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for HANWARE HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HANWARE HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2024, already 42 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HANWARE HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "REASON FOR DELAY ARE 1) COVID-19 LOCKDOWN 2) SHORTAGE OF LABOUR DUE TO MIGRATION OF LABOURS TO THEIR NATIVE PLACES. 3) SHORTAGE OF CONSTRUCTION MATERIALS DUE TO COVID-19 LOCKDOWN 4) INCREASED COVID-19 CASES IN DHARAVI WHERE OUR PROJECT IS SITUATED."; to 30 June 2023, giving the reason "SHORTAGE OF LABOURS AND BUILDING MATERIALS DUE TO COVID 19"; to 31 December 2024, giving the reason "Construction work is stopped in the Covid 19 period due to the increased cases in Dharavi area where project is situated. After that construction work got slow for few months due to migration of labours in their villages because of Covid 19 lockdown. The our allottees are aware of all our problems and they are co-operating with us and have given their consents for extension. We request the authority to please give us further extension to complete the project.".

What is the RERA number of HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HANWARE HEIGHTS in Dharavi, Mumbai is P51900019260.

Is HANWARE HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS is registered as P51900019260 and its status is "Lapsed (registration period ended)".

What is the construction status of HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on HANWARE HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does HANWARE HEIGHTS have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HANWARE HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS is registered on MahaRERA as P51900019260, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HANWARE HEIGHTS's possession date changes?

The latest dates are on HANWARE HEIGHTS's MahaRERA page (P51900019260). GharKundli's Kundli Watch sends a free WhatsApp update on HANWARE HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HANWARE HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS has one building filed: HANWARE HEIGHTS with 20 floors.

How big is the land of HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS stands on 2,541 sq m of land (about 0.6 acres), with 8,785 sq m of sanctioned built-up area.

What is the track record of HANWARE HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Hanware Realty (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 7 months). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HANWARE HEIGHTS?

Google Maps has reviews of HANWARE HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HANWARE HEIGHTS?

HANWARE HEIGHTS by HANWARE REALTY is in Dharavi, Mumbai (pincode 400017), near Matunga, Sion West, Mahim, Maharashtra, and is registered on MahaRERA as P51900019260, per GharKundli's check of MahaRERA records.

How many homes are in HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS has 112 homes in 1 tower registered on MahaRERA.

When was HANWARE HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HANWARE HEIGHTS was registered on MahaRERA on 14 January 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on HANWARE HEIGHTS?

7 court cases are listed for HANWARE HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of HANWARE HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HANWARE REALTY.

Other projects in pincode 400017

All 9 projects in Dharavi (400017) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.