MADHUBAN F1 F2
by Abhilasha Venture · Titwala, Thane
Registered on MahaRERA under P51700002614. Status: Completed. Its completion date has moved from March 2019 to September 2020, 18 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on MADHUBAN F1 F2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700002614
- Status
- Completed
- Builder
- Abhilasha Venture
- Location
- Titwala, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 2 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- September 2020
- Delay so far
- 18 months
- Homes
- 56
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
MADHUBAN F1 F2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MADHUBAN F1 F2
Is MADHUBAN F1 F2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN F1 F2 is registered as P51700002614 and its status is "Completed".
Where is MADHUBAN F1 F2?
MADHUBAN F1 F2 by Abhilasha Venture is in Titwala, Thane (pincode 421605), Maharashtra, and is registered on MahaRERA as P51700002614, per GharKundli's check of MahaRERA records.
When is possession of MADHUBAN F1 F2 due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MADHUBAN F1 F2 in Titwala, Thane is 30 September 2020 — 18 months later than 31 March 2019, the date given at registration.
Does MADHUBAN F1 F2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in MADHUBAN F1 F2?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN F1 F2 has 56 homes in 2 towers registered on MahaRERA.
When was MADHUBAN F1 F2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN F1 F2 was registered on MahaRERA on 2 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MADHUBAN F1 F2?
1 court case is listed for MADHUBAN F1 F2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MADHUBAN F1 F2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Abhilasha Venture, which has 1 other project registered on MahaRERA.
Other projects in pincode 421605
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.