MARATHE TOWER
by SAIJI DEVELOPERS · Manda Village, Thane
Possession date of MARATHE TOWER: 30 April 2027, moved from 30 March 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700022652, and currently active. Its completion date has moved from March 2026 to April 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MARATHE TOWER?
How the possession date of MARATHE TOWER has moved
30 March 2026
Completion date given when the project was registered
30 July 2026
Extended at the builder's request (MahaRERA application EA02032620056)
Reason the builder gave MahaRERA: “Shortage of labour and delay from KDMC in receiving necessary approvals”
31 December 2026
Extended at the builder's request (MahaRERA application EA17072621778)
Reason the builder gave MahaRERA: “shortage of manpower and labour”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MARATHE TOWER’s extension records on MahaRERA (P51700022652), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MARATHE TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700022652
- Status
- Registered and active
- Builder
- SAIJI DEVELOPERS
- Location
- Manda Village, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 9 Oct 2019
- Completion date at registration
- March 2026
- Latest completion date
- April 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 191
- Sold or booked
- 34%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of MARATHE TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MARATHE TOWER WING A | 100% | 100% | 90% | 70% |
| MARATHE TOWER WING B | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MARATHE TOWER WING A: covers 31 floors
- MARATHE TOWER WING B: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARATHE TOWER every month.
MARATHE TOWER: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 377 – 577 | 154 |
| 2 BHK | 571 – 577 | 37 |
| Shops | 40 – 298 | 27 |
- Buildings: MARATHE TOWER WING A (66 floors, 198 units) · MARATHE TOWER WING B (8 floors, 20 units)
- Car parking: 26 covered, 10 open
- Land: 4,500 sq m (about 1.1 acres) · recreational space 300 sq m
The builder’s record and reviews
Saiji Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of MARATHE TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MARATHE TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MARATHE TOWER
What is the possession date of MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MARATHE TOWER in Manda Village, Thane is 30 April 2027 — 9 months later than 30 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MARATHE TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MARATHE TOWER's builder has filed on MahaRERA, the official one, is 30 April 2027, already 9 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MARATHE TOWER extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2026, giving the reason "Shortage of labour and delay from KDMC in receiving necessary approvals"; to 31 December 2026, giving the reason "shortage of manpower and labour". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MARATHE TOWER in Manda Village, Thane is P51700022652.
Is MARATHE TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER is registered as P51700022652 and its status is "Registered and active".
What is the construction status of MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does MARATHE TOWER have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MARATHE TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER is registered on MahaRERA as P51700022652, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MARATHE TOWER's possession date changes?
The latest dates are on MARATHE TOWER's MahaRERA page (P51700022652). GharKundli's Kundli Watch sends a free WhatsApp update on MARATHE TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MARATHE TOWER have?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER has 2 buildings filed: MARATHE TOWER WING A with 66 floors and 198 units; MARATHE TOWER WING B with 8 floors and 20 units.
What are the flat sizes (carpet area) in MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MARATHE TOWER: 1 BHK: 377 to 577 sq ft carpet (154 homes); 2 BHK: 571 to 577 sq ft carpet (37 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does MARATHE TOWER have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered and 10 open car parking spaces for MARATHE TOWER.
How big is the land of MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER stands on 4,500 sq m of land (about 1.1 acres) and 300 sq m of recreational open space.
What is the track record of MARATHE TOWER's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Saiji Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MARATHE TOWER?
Google Maps has reviews of MARATHE TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MARATHE TOWER?
MARATHE TOWER by SAIJI DEVELOPERS is in Manda Village, Thane (pincode 421605), Maharashtra, and is registered on MahaRERA as P51700022652, per GharKundli's check of MahaRERA records.
How many homes are in MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER has 191 homes in 2 towers registered on MahaRERA, and 34% of them are sold or booked.
When was MARATHE TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE TOWER was registered on MahaRERA on 9 October 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on MARATHE TOWER?
No court cases are listed for MARATHE TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MARATHE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAIJI DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MARATHE TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421605
- CHARMS CITY PHASE II
- MARATHE ELENZA
- GANPATI HEIGHTS
- SHREE GAJANAN PLAZA
- SARNOBAT RESIDENCY
- PITAMBARE TOWER
- MANGALMURTI HEIGHTS
- SAI VRINDAVAN
Other projects by SAIJI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.