PITAMBARE TOWER
by ADITI BUILDERS AND DEVELOPERS · Khadavali, ThaneAlso near Manda
Possession date of PITAMBARE TOWER: 31 July 2028, moved from 31 December 2025 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055596, and currently active. Its completion date has moved from December 2025 to July 2028: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PITAMBARE TOWER?
How the possession date of PITAMBARE TOWER has moved
31 December 2025
Completion date given when the project was registered
31 March 2028
Extended at the builder's request (MahaRERA application EA05032620104)
Reason the builder gave MahaRERA:
“Project got delayed due to acute liquidity constraints on account of nonavailability of adequate internal accruals of cash flows and delay in arranging external project finance from financial institutions. Owing to the constrained cash flow…” Read the full reason
“Project got delayed due to acute liquidity constraints on account of nonavailability of adequate internal accruals of cash flows and delay in arranging external project finance from financial institutions. Owing to the constrained cash flow position, the Promoter was unable to mobilize sufficient funds for procurement of construction materials, appointment of contractors, and commencement of construction activities as originally planned. It is further submitted that the delay is purely on account of temporary financial hardship and not due to any intentional act or negligence. No flats/unit…”31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PITAMBARE TOWER’s extension records on MahaRERA (P51700055596), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PITAMBARE TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055596
- Status
- Registered and active
- Builder
- ADITI BUILDERS AND DEVELOPERS
- Location
- Khadavali, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 4 Apr 2024
- Completion date at registration
- December 2025
- Latest completion date
- July 2028
- Delay so far
- 27 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 29
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of PITAMBARE TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PITAMBARE TOWER | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PITAMBARE TOWER: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PITAMBARE TOWER every month.
PITAMBARE TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: PITAMBARE TOWER (6 floors, 29 units)
- Land: 900 sq m (about 0.2 acres) · sanctioned built-up 1,439 sq m
- Boundaries filed include: TWENTY FEET ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PITAMBARE TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PITAMBARE TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PITAMBARE TOWER
What is the possession date of PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PITAMBARE TOWER in Khadavali, Thane is 31 July 2028 — 27 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PITAMBARE TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PITAMBARE TOWER's builder has filed on MahaRERA, the official one, is 31 July 2028, already 27 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PITAMBARE TOWER extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "Project got delayed due to acute liquidity constraints on account of nonavailability of adequate internal accruals of cash flows and delay in arranging external project finance from financial institutions. Owing to the constrained cash flow position, the Promoter was unable to mobilize sufficient funds for procurement of construction materials, appointment of contractors, and commencement of construction activities as originally planned. It is further submitted that the delay is purely on account of temporary financial hardship and not due to any intentional act or negligence. No flats/unit…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PITAMBARE TOWER in Khadavali, Thane is P51700055596.
Is PITAMBARE TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER is registered as P51700055596 and its status is "Registered and active".
What is the construction status of PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PITAMBARE TOWER is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does PITAMBARE TOWER have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is PITAMBARE TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER is registered on MahaRERA as P51700055596, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PITAMBARE TOWER's possession date changes?
The latest dates are on PITAMBARE TOWER's MahaRERA page (P51700055596). GharKundli's Kundli Watch sends a free WhatsApp update on PITAMBARE TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PITAMBARE TOWER have?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER has one building filed: PITAMBARE TOWER with 6 floors and 29 units.
How big is the land of PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER stands on 900 sq m of land (about 0.2 acres), with 1,439 sq m of sanctioned built-up area.
Where can I read reviews of PITAMBARE TOWER?
Google Maps has reviews of PITAMBARE TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PITAMBARE TOWER?
PITAMBARE TOWER by ADITI BUILDERS AND DEVELOPERS is in Khadavali, Thane (pincode 421605), near Manda, Maharashtra, and is registered on MahaRERA as P51700055596, per GharKundli's check of MahaRERA records. Its boundaries filed there include TWENTY FEET ROAD.
How many homes are in PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER has 29 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was PITAMBARE TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PITAMBARE TOWER was registered on MahaRERA on 4 April 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on PITAMBARE TOWER?
No court cases are listed for PITAMBARE TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PITAMBARE TOWER?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITI BUILDERS AND DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PITAMBARE TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 421605
- CHARMS CITY PHASE II
- MARATHE ELENZA
- MARATHE TOWER
- GANPATI HEIGHTS
- SHREE GAJANAN PLAZA
- SARNOBAT RESIDENCY
- MANGALMURTI HEIGHTS
- SAI VRINDAVAN
Other projects by ADITI BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.