MARATHE ELENZA
by SAIJI DEVELOPERS · titwala, ThaneAlso near Manda
Possession date of MARATHE ELENZA: 30 November 2026, moved from 30 March 2026 (4 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700010396, and currently active. Its completion date has moved from March 2026 to November 2026: 4 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MARATHE ELENZA?
How the possession date of MARATHE ELENZA has moved
30 March 2026
Completion date given when the project was registered
31 July 2026
Extended at the builder's request (MahaRERA application EA22042620686)
Reason the builder gave MahaRERA: “we have already received OC from KDMC however we are filing for extension so that we can do a correction update on the project and file again for completion. The Occupation certificate is attached. Please grant an extension urgently.”
30 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MARATHE ELENZA’s extension records on MahaRERA (P51700010396), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MARATHE ELENZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700010396
- Status
- Registered and active
- Builder
- SAIJI DEVELOPERS
- Location
- titwala, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- March 2026
- Latest completion date
- November 2026
- Delay so far
- 4 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Sold or booked
- 29%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of MARATHE ELENZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MARATHE ELENZA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MARATHE ELENZA: covers 24 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARATHE ELENZA every month.
MARATHE ELENZA: buildings, flats and land, as filed on MahaRERA
- Buildings: MARATHE ELENZA (29 floors, 49 units)
- Car parking: 4 covered, 15 open
- Land: 3,140 sq m (about 0.8 acres) · sanctioned built-up 1,715 sq m
The builder’s record and reviews
Saiji Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of MARATHE ELENZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MARATHE ELENZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MARATHE ELENZA
What is the possession date of MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MARATHE ELENZA in titwala, Thane is 30 November 2026 — 4 months later than 30 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MARATHE ELENZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MARATHE ELENZA's builder has filed on MahaRERA, the official one, is 30 November 2026, already 4 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MARATHE ELENZA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA's builder applied to MahaRERA to extend the completion date once: to 31 July 2026, giving the reason "we have already received OC from KDMC however we are filing for extension so that we can do a correction update on the project and file again for completion. The Occupation certificate is attached. Please grant an extension urgently.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MARATHE ELENZA in titwala, Thane is P51700010396.
Is MARATHE ELENZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA is registered as P51700010396 and its status is "Registered and active".
What is the construction status of MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MARATHE ELENZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MARATHE ELENZA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MARATHE ELENZA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA is registered on MahaRERA as P51700010396, its completion date has moved 4 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MARATHE ELENZA's possession date changes?
The latest dates are on MARATHE ELENZA's MahaRERA page (P51700010396). GharKundli's Kundli Watch sends a free WhatsApp update on MARATHE ELENZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MARATHE ELENZA have?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA has one building filed: MARATHE ELENZA with 29 floors and 49 units.
How much parking does MARATHE ELENZA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered and 15 open car parking spaces for MARATHE ELENZA.
How big is the land of MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA stands on 3,140 sq m of land (about 0.8 acres), with 1,715 sq m of sanctioned built-up area.
What is the track record of MARATHE ELENZA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Saiji Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MARATHE ELENZA?
Google Maps has reviews of MARATHE ELENZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MARATHE ELENZA?
MARATHE ELENZA by SAIJI DEVELOPERS is in titwala, Thane (pincode 421605), near Manda, Maharashtra, and is registered on MahaRERA as P51700010396, per GharKundli's check of MahaRERA records.
How many homes are in MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA has 46 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.
When was MARATHE ELENZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MARATHE ELENZA was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MARATHE ELENZA?
No court cases are listed for MARATHE ELENZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MARATHE ELENZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAIJI DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MARATHE ELENZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in pincode 421605
- CHARMS CITY PHASE II
- MARATHE TOWER
- GANPATI HEIGHTS
- SHREE GAJANAN PLAZA
- SARNOBAT RESIDENCY
- PITAMBARE TOWER
- MANGALMURTI HEIGHTS
- SAI VRINDAVAN
Other projects by SAIJI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.