Possession date of Durahomes Builders and developers pvt ltd: 30 November 2028. This is the latest completion date the builder has filed on MahaRERA.
Registered on MahaRERA under P51700012518, and currently active. Its completion date is now November 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on Durahomes Builders and developers pvt ltd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700012518
- Status
- Registered and active
- Builder
- Arshad Ahmed Siddiqui
- Location
- chavindra, Thane · 421302
- Project type
- Mixed
- Registered on
- 1 Sep 2017
- Completion date at registration
- July 2028
- Latest completion date
- November 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 43
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 5
- Title report on file
- Not found
Construction progress of Durahomes Builders and developers pvt ltd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| building G | 100% | 90% | 70% | 0% |
| Building F | 100% | 100% | 70% | 0% |
| Building E | 0% | 60% | 50% | 0% |
| Building KM 1 | 80% | 100% | 80% | 0% |
| Building KL 1 | 90% | 90% | 90% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Durahomes Builders and developers pvt ltd every month.
Durahomes Builders and developers pvt ltd: buildings, flats and land, as filed on MahaRERA
- Buildings: building G (2 floors) · Building F (2 floors) · Building KM 1 (2 floors) · Building KL 1 (2 floors)
- Land: 1,26,668 sq m (about 31.3 acres) · sanctioned built-up 69,515 sq m · recreational space 13,439 sq m
- Boundaries filed include: Mumbai Nashik Road
- Map: the location the builder filed on MahaRERA
Kundli Watch
Durahomes Builders and developers pvt ltd: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Durahomes Builders and developers pvt ltd
What is the possession date of Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Durahomes Builders and developers pvt ltd in chavindra, Thane is 30 November 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Durahomes Builders and developers pvt ltd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Durahomes Builders and developers pvt ltd's builder has filed on MahaRERA, the official one, is 30 November 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Durahomes Builders and developers pvt ltd in chavindra, Thane is P51700012518.
Is Durahomes Builders and developers pvt ltd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd is registered as P51700012518 and its status is "Registered and active".
What is the construction status of Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 60% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Durahomes Builders and developers pvt ltd have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Durahomes Builders and developers pvt ltd safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd is registered on MahaRERA as P51700012518, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Durahomes Builders and developers pvt ltd's possession date changes?
The latest dates are on Durahomes Builders and developers pvt ltd's MahaRERA page (P51700012518). GharKundli's Kundli Watch sends a free WhatsApp update on Durahomes Builders and developers pvt ltd every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Durahomes Builders and developers pvt ltd have?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd has 4 buildings filed: building G with 2 floors; Building F with 2 floors; Building KM 1 with 2 floors; Building KL 1 with 2 floors.
How big is the land of Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd stands on 1,26,668 sq m of land (about 31.3 acres), with 69,515 sq m of sanctioned built-up area and 13,439 sq m of recreational open space.
Where is Durahomes Builders and developers pvt ltd?
Durahomes Builders and developers pvt ltd by Arshad Ahmed Siddiqui is in chavindra, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700012518, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mumbai Nashik Road.
How many homes are in Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd has 43 homes in 5 towers registered on MahaRERA.
When was Durahomes Builders and developers pvt ltd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Durahomes Builders and developers pvt ltd was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Durahomes Builders and developers pvt ltd?
5 court cases are listed for Durahomes Builders and developers pvt ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Durahomes Builders and developers pvt ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Arshad Ahmed Siddiqui.
All projects with possession due in 2028 in Thane →
All projects in Bhiwandi (421302) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.