Skip to content
GharKundli

BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2

by GROW MORE INFRACON · Shahapur S.O (Thane), Thane

Possession date of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2: 30 December 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed.

Registered on MahaRERA under P51700011914. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

GharKundli’s full report on BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700011914
Status
Lapsed (registration period ended)
Builder
GROW MORE INFRACON
Location
Shahapur S.O (Thane), Thane · 421601
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2021
Homes
144
Towers
6
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%100%
B WING100%100%100%100%
C WING100%100%100%100%
D WING100%100%100%100%
E WING100%100%100%100%
F WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 every month.

BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (5 floors) · B WING (5 floors) · C WING (5 floors) · D WING (5 floors) · E WING (5 floors) · F WING (5 floors)
  • Land: 7,775 sq m (about 1.9 acres) · sanctioned built-up 5,817 sq m

Kundli Watch

BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2

What is the possession date of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 in Shahapur S.O (Thane), Thane is 30 December 2021. That date has already passed.

Is the builder's possession date different from the MahaRERA date for BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2's builder has filed on MahaRERA, the official one, is 30 December 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 in Shahapur S.O (Thane), Thane is P51700011914.

Is BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 is registered as P51700011914 and its status is "Lapsed (registration period ended)".

What is the construction status of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 is registered on MahaRERA as P51700011914, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2's possession date changes?

The latest dates are on BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2's MahaRERA page (P51700011914). GharKundli's Kundli Watch sends a free WhatsApp update on BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 has 6 buildings filed: A WING with 5 floors; B WING with 5 floors; C WING with 5 floors; D WING with 5 floors; E WING with 5 floors; F WING with 5 floors.

How big is the land of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 stands on 7,775 sq m of land (about 1.9 acres), with 5,817 sq m of sanctioned built-up area.

Where is BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 by GROW MORE INFRACON is in Shahapur S.O (Thane), Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700011914, per GharKundli's check of MahaRERA records.

How many homes are in BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 has 144 homes in 6 towers registered on MahaRERA.

When was BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

No court cases are listed for BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BUILDING NO 4 PHASE I PART OF VARDHAMAN VATIKA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GROW MORE INFRACON.

Other projects in pincode 421601

All 170 projects in Shahapur (421601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.