Pitruchhaya Apartment

by The Finest Housing Company · Tulsi Vihar, Thane

Possession date of Pitruchhaya Apartment: 30 October 2027, moved from 31 March 2025 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700051889, and currently active. Its completion date has moved from March 2025 to October 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Pitruchhaya Apartment?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Pitruchhaya Apartment has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51700028078)

    Reason the builder gave MahaRERA: “Project was in abeyance and account was freezed”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA04062621226)

    Reason the builder gave MahaRERA: “Due to some technical problem we are not able to complete project on time”
  4. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Pitruchhaya Apartment’s extension records on MahaRERA (P51700051889), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Pitruchhaya Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700051889
Status
Registered and active
Builder
The Finest Housing Company
Location
Tulsi Vihar, Thane · 421601
Project type
Residential / Group Housing
Registered on
7 Jul 2023
Completion date at registration
March 2025
Latest completion date
October 2027
Delay so far
27 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
15
Sold or booked
27%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Pitruchhaya Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Pitruchhaya Apartment100%90%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • Pitruchhaya Apartment: covers 5 floors

Latest CC order on MahaRERA: dated 07/02/2023.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pitruchhaya Apartment every month.

Pitruchhaya Apartment: buildings, flats and land, as filed on MahaRERA

  • Buildings: Pitruchhaya Apartment (6 floors, 15 units)
  • Car parking: 1 covered
  • Land: 268 sq m (about 0.1 acres) · sanctioned built-up 600 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Pitruchhaya Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Pitruchhaya Apartment: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Pitruchhaya Apartment

What is the possession date of Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pitruchhaya Apartment in Tulsi Vihar, Thane is 30 October 2027 — 27 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Pitruchhaya Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Pitruchhaya Apartment's builder has filed on MahaRERA, the official one, is 30 October 2027, already 27 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Pitruchhaya Apartment extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Project was in abeyance and account was freezed"; to 30 June 2027, giving the reason "Due to some technical problem we are not able to complete project on time". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pitruchhaya Apartment in Tulsi Vihar, Thane is P51700051889.

Is Pitruchhaya Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment is registered as P51700051889 and its status is "Registered and active".

What is the construction status of Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Pitruchhaya Apartment is 90% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does Pitruchhaya Apartment have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Pitruchhaya Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment is registered on MahaRERA as P51700051889, its completion date has moved 27 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Pitruchhaya Apartment's possession date changes?

The latest dates are on Pitruchhaya Apartment's MahaRERA page (P51700051889). GharKundli's Kundli Watch sends a free WhatsApp update on Pitruchhaya Apartment every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Pitruchhaya Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment has one building filed: Pitruchhaya Apartment with 6 floors and 15 units.

How much parking does Pitruchhaya Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Pitruchhaya Apartment.

How big is the land of Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment stands on 268 sq m of land (about 0.1 acres), with 600 sq m of sanctioned built-up area.

Where can I read reviews of Pitruchhaya Apartment?

Google Maps has reviews of Pitruchhaya Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Pitruchhaya Apartment?

Pitruchhaya Apartment by The Finest Housing Company is in Tulsi Vihar, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700051889, per GharKundli's check of MahaRERA records.

How many homes are in Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment has 15 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.

When was Pitruchhaya Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pitruchhaya Apartment was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Pitruchhaya Apartment?

No court cases are listed for Pitruchhaya Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Pitruchhaya Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is The Finest Housing Company.

All projects with possession due in 2027 in Thane →

Other projects in Shahapur

All 184 projects in Shahapur (421601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.