by St. Angelo's VNCT Ventures Pvt. Ltd. · Shahapur, Thane 420601Also near Shahapur, Cherpoli, Rahul Nagar

What’s in the report? →

Possession date of The White Villas (MahaRERA P51700000038): 30 April 2027, moved from 30 June 2021 (66 months later). It has 43 homes (3 BHK and 5 BHK, 774–1882 sq ft carpet), 77% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700000038, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700000038, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The White Villas?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The White Villas has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51700010008)

    Reason the builder gave MahaRERA: “Due to Covid 19 the project was not able to get completed in time. We would like to request you to further grant us extension for 12 month.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51700013462)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51700018668)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2026”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The White Villas’s extension records on MahaRERA (P51700000038), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The White Villas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700000038
Status
Registered and active
Builder
St. Angelo's VNCT Ventures Pvt. Ltd.
Location
Shahapur, Thane · 420601
Project type
Residential / Group Housing
Registered on
16 Jun 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
43
Sold or booked
77%
Towers
43
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of The White Villas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ZEUS VILLA NO 180%80%80%100%
ATLANTIS VILLA NO 280%80%80%100%
APHRODITE VILLA NO 380%80%80%100%
APOLLO VILLA NO 480%80%80%100%
ARTEMIS VILLA NO 580%80%80%100%
ASTRAEA VILLA NO 680%80%80%100%
ATHENA VILLA NO 780%80%80%100%
ATLAS VILLA NO 880%80%80%100%
ATTIS VILLA NO 980%80%80%100%
BIA VILLA NO 1080%80%80%100%
CASTOR VILLA NO 1180%80%80%100%
CERUS VILLA NO 1280%80%80%100%
KETO VILLA NO 1380%80%80%100%
CLIO VILLA NO 1480%80%80%100%
CRONUS VILLA NO 1580%80%80%100%
CYBELE VILLA NO 1680%80%80%100%
DEMETER VILLA NO 1780%80%80%100%
ELECTRA VILLA NO 1880%80%80%100%
EOS VILLA NO 1980%80%80%100%
ERATO VILLA NO 2080%80%80%100%
EROS VILLA NO 2180%80%80%100%
GAIA VILLA NO 2280%80%80%100%
HARMONIA VILLA NO 2380%80%80%100%
ZEPHYR VILLA NO 2480%80%80%100%
HELIOS VILLA NO 2580%80%80%100%
HEMERA VILLA NO 2680%80%80%100%
HERA VILLA NO 2780%80%80%100%
URANIA VILLA NO 2880%80%80%100%
HERMES VILLA NO 2980%80%80%200%
HESPERUS VILLA NO 3080%80%80%100%

Showing 30 of 43 towers.

Commencement certificate (CC), as filed on MahaRERA

  • ZEUS VILLA NO 1: covers plinth level
  • ATLANTIS VILLA NO 2: covers plinth level
  • APHRODITE VILLA NO 3: covers plinth level
  • APOLLO VILLA NO 4: covers plinth level
  • ARTEMIS VILLA NO 5: covers plinth level
  • ASTRAEA VILLA NO 6: covers plinth level
  • ATHENA VILLA NO 7: covers plinth level
  • ATLAS VILLA NO 8: covers plinth level
  • ATTIS VILLA NO 9: covers plinth level
  • BIA VILLA NO 10: covers plinth level
  • CASTOR VILLA NO 11: covers plinth level
  • CERUS VILLA NO 12: covers plinth level
  • KETO VILLA NO 13: covers plinth level
  • CLIO VILLA NO 14: covers plinth level
  • CRONUS VILLA NO 15: covers plinth level
  • CYBELE VILLA NO 16: covers plinth level
  • DEMETER VILLA NO 17: covers plinth level
  • ELECTRA VILLA NO 18: covers plinth level
  • EOS VILLA NO 19: covers plinth level
  • ERATO VILLA NO 20: covers plinth level
  • EROS VILLA NO 21: covers plinth level
  • GAIA VILLA NO 22: covers plinth level
  • HARMONIA VILLA NO 23: covers plinth level
  • ZEPHYR VILLA NO 24: covers plinth level
  • HELIOS VILLA NO 25: covers plinth level
  • HEMERA VILLA NO 26: covers plinth level
  • HERA VILLA NO 27: covers plinth level
  • URANIA VILLA NO 28: covers plinth level
  • HERMES VILLA NO 29: covers plinth level
  • HESPERUS VILLA NO 30: covers plinth level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The White Villas every 1–2 months.

The White Villas: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK774 – 93929
5 BHK1,556 – 1,88214
  • Buildings: ZEUS VILLA NO 1 (2 floors, 1 units) · ATLANTIS VILLA NO 2 (2 floors, 1 units) · APHRODITE VILLA NO 3 (2 floors, 1 units) · APOLLO VILLA NO 4 (2 floors, 1 units) · ARTEMIS VILLA NO 5 (2 floors, 1 units) · ASTRAEA VILLA NO 6 (2 floors, 1 units) · ATHENA VILLA NO 7 (2 floors, 1 units) · ATLAS VILLA NO 8 (2 floors, 1 units) · and 22 more
  • Land: 8,000 sq m (about 2.0 acres) · sanctioned built-up 7,200 sq m · recreational space 800 sq m
  • Land, as filed: 420/1
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

St Angelo's Vnct Ventures has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 48 months late). No complaints on MahaRERA.

Read Google reviews of The White Villas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The White Villas: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The White Villas

What is the possession date of The White Villas?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The White Villas in Shahapur, Thane is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The White Villas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The White Villas's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The White Villas extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to Covid 19 the project was not able to get completed in time. We would like to request you to further grant us extension for 12 month."; to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023"; to 31 December 2026, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of The White Villas?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The White Villas in Shahapur, Thane is P51700000038.

Is The White Villas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas is registered as P51700000038 and its status is "Registered and active".

What is the current construction status of The White Villas? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 80% done across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does The White Villas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The White Villas safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas is registered on MahaRERA as P51700000038, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The White Villas?

The White Villas is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The White Villas?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The White Villas: gharkundli.com/tools/property-cost-calculator

Has The White Villas received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has The White Villas uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The White Villas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The White Villas's possession date changes?

The latest dates are on The White Villas's MahaRERA page (P51700000038). GharKundli's Kundli Watch sends a free WhatsApp update on The White Villas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The White Villas have?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas has 30 buildings filed: ZEUS VILLA NO 1 with 2 floors and 1 units; ATLANTIS VILLA NO 2 with 2 floors and 1 units; APHRODITE VILLA NO 3 with 2 floors and 1 units; APOLLO VILLA NO 4 with 2 floors and 1 units; ARTEMIS VILLA NO 5 with 2 floors and 1 units; ASTRAEA VILLA NO 6 with 2 floors and 1 units; and 24 more.

What are the flat sizes (carpet area) in The White Villas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The White Villas: 3 BHK: 774 to 939 sq ft carpet (29 homes); 5 BHK: 1556 to 1882 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of The White Villas?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas stands on 8,000 sq m of land (about 2.0 acres), with 7,200 sq m of sanctioned built-up area and 800 sq m of recreational open space.

What is the track record of The White Villas's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), St Angelo's Vnct Ventures has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 48 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of The White Villas?

Google Maps has reviews of The White Villas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The White Villas?

The White Villas by St. Angelo's VNCT Ventures Pvt. Ltd. is in Shahapur, Thane, pincode 420601 (near Shahapur, Cherpoli, Rahul Nagar), Maharashtra, and is registered on MahaRERA as P51700000038, per GharKundli's check of MahaRERA records. Its land is filed as 420/1.

How many flats are in The White Villas, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas has 43 homes in 43 towers registered on MahaRERA, and 77% of them are sold or booked.

When was The White Villas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The White Villas was registered on MahaRERA on 16 June 2017. GharKundli did not find a title report on the land on file there.

Does The White Villas have any legal issues or court cases?

No court cases are listed for The White Villas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The White Villas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is St. Angelo's VNCT Ventures Pvt. Ltd., which has 2 other projects registered on MahaRERA.

Other projects in Shahapur

Other projects by St. Angelo's VNCT Ventures Pvt. Ltd.

All Thane projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.