Skip to content
GharKundli

Lodha NCP Tower - 2

by LODHA DEVELOPERS LIMITED · Wadala, Mumbai 400022

What’s in the report? →

Possession date of Lodha NCP Tower - 2 (MahaRERA P51900046324): 30 October 2030, moved from 31 May 2029 (13 months later). It has 220 homes (3 BHK and 4 BHK, 811–1478 sq ft carpet), 41% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900046324, and currently active. Its completion date has moved from May 2029 to October 2030: 13 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900046324, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Lodha NCP Tower - 2?

3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lodha NCP Tower - 2 has moved

  1. 31 May 2029

    Completion date given when the project was registered

  2. 30 June 2030

    Extended at the builder's request (MahaRERA application EXT51900027714)

    Reason the builder gave MahaRERA:
    “Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late s tart of construction work. As of Now ,at the time of extension request no allotees in this…” Read the full reason“Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late s tart of construction work. As of Now ,at the time of extension request no allotees in this project.”
  3. 30 October 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lodha NCP Tower - 2’s extension records on MahaRERA (P51900046324), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lodha NCP Tower - 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 court cases, and how it ended
  • Construction pace against the October 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51900046324
Status
Registered and active
Builder
LODHA DEVELOPERS LIMITED
Location
Wadala, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
22 Jun 2022
Completion date at registration
May 2029
Latest completion date
October 2030
Delay so far
13 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
220
Sold or booked
41%
Towers
1
Complaints on MahaRERA
0
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Lodha NCP Tower - 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower 2100%18%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower 2: covers Plinth

Latest CC order on MahaRERA: dated 21/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha NCP Tower - 2 every 1–2 months.

Lodha NCP Tower - 2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other811 – 1,475117
3 BHK96472
4 BHK1,47831
  • Buildings: Tower 2 (45 floors, 220 units)
  • Car parking: 440 covered
  • Land: 2,226 sq m (about 0.5 acres) · sanctioned built-up 23,691 sq m · recreational space 779 sq m
  • Land, as filed: BLOCK C, WTT, CS. NO 8 pt Saltpan Division
  • Map: Get directions

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Lodha NCP Tower - 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha NCP Tower - 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lodha NCP Tower - 2

What is the possession date of Lodha NCP Tower - 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha NCP Tower - 2 in Wadala, Mumbai is 30 October 2030 — 13 months later than 31 May 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 13 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Lodha NCP Tower - 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha NCP Tower - 2's builder has filed on MahaRERA, the official one, is 30 October 2030, already 13 months later than the 31 May 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lodha NCP Tower - 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2's builder applied to MahaRERA to extend the completion date once: to 30 June 2030, giving the reason "Due to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late s tart of construction work. As of Now ,at the time of extension request no allotees in this project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Lodha NCP Tower - 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha NCP Tower - 2 in Wadala, Mumbai is P51900046324.

Is Lodha NCP Tower - 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 is registered as P51900046324 and its status is "Registered and active".

What is the current construction status of Lodha NCP Tower - 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tower 2 is 18% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Lodha NCP Tower - 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lodha NCP Tower - 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 is registered on MahaRERA as P51900046324, its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lodha NCP Tower - 2?

Lodha NCP Tower - 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Lodha NCP Tower - 2 start at 811 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lodha NCP Tower - 2?

For a flat in Lodha NCP Tower - 2 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lodha NCP Tower - 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 is still under construction, with 30 October 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Lodha NCP Tower - 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha NCP Tower - 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Lodha NCP Tower - 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Lodha NCP Tower - 1 (P51900034170, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.

How can I get updates if Lodha NCP Tower - 2's possession date changes?

The latest dates are on Lodha NCP Tower - 2's MahaRERA page (P51900046324). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha NCP Tower - 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha NCP Tower - 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 has one building filed: Tower 2 with 45 floors and 220 units.

What are the flat sizes (carpet area) in Lodha NCP Tower - 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lodha NCP Tower - 2: Other: 811 to 1475 sq ft carpet (117 homes); 3 BHK: 964 sq ft carpet (72 homes); 4 BHK: 1478 sq ft carpet (31 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Lodha NCP Tower - 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 440 covered car parking spaces for Lodha NCP Tower - 2.

How big is the land of Lodha NCP Tower - 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 stands on 2,226 sq m of land (about 0.5 acres), with 23,691 sq m of sanctioned built-up area and 779 sq m of recreational open space.

What is the track record of Lodha NCP Tower - 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lodha NCP Tower - 2?

Google Maps has reviews of Lodha NCP Tower - 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lodha NCP Tower - 2?

Lodha NCP Tower - 2 by LODHA DEVELOPERS LIMITED is in Wadala, Mumbai, pincode 400022, Maharashtra, and is registered on MahaRERA as P51900046324, per GharKundli's check of MahaRERA records. Its land is filed as BLOCK C, WTT, CS. NO 8 pt Saltpan Division. GharKundli lists all 98 MahaRERA projects in Sion (400022).

How many flats are in Lodha NCP Tower - 2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 has 220 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.

When was Lodha NCP Tower - 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha NCP Tower - 2 was registered on MahaRERA on 22 June 2022. GharKundli did not find a title report on the land on file there.

Does Lodha NCP Tower - 2 have any legal issues or court cases?

3 court cases are listed for Lodha NCP Tower - 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Lodha NCP Tower - 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LODHA DEVELOPERS LIMITED, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai City →

Other projects in Sion (400022)

All 98 projects in Sion (400022) →

Other projects by LODHA DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.