Skip to content
GharKundli

Dignity Bayview

by DIGNITY REALTY AND HOUSING · Wadala west, MumbaiAlso near Matunga, Dadar East, Hindu Colony

Possession date of Dignity Bayview: 31 July 2027, moved from 31 December 2026 (7 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900048008, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Dignity Bayview?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Dignity Bayview has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 31 July 2027

    Extended at the builder's request (MahaRERA application EA01082621982)

    Reason the builder gave MahaRERA:
    “The delay in completion of the Project is primarily attributable to the statutory process involved in obtaining the Environmental Clearance (EC), which was applied for on 30/06/2025 and granted by SEIAA, Maharashtra on 23/12/2025, resulting…” Read the full reason“The delay in completion of the Project is primarily attributable to the statutory process involved in obtaining the Environmental Clearance (EC), which was applied for on 30/06/2025 and granted by SEIAA, Maharashtra on 23/12/2025, resulting in a material impact on the Project execution schedule. Subsequently, procurement constraints, financial limitations, and site-specific execution challenges further affected the progress of the balance works; accordingly, we request an extension until 31/07/2027 to complete the Project and fulfil all applicable regulatory requirements.”

Source: Dignity Bayview’s extension records on MahaRERA (P51900048008), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dignity Bayview

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900048008
Status
Registered and active
Builder
DIGNITY REALTY AND HOUSING
Location
Wadala west, Mumbai · 400031
Project type
Residential / Group Housing
Registered on
7 Dec 2022
Completion date at registration
December 2026
Latest completion date
July 2027
Delay so far
7 months
Homes
179
Sold or booked
58%
Towers
2
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Dignity Bayview, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DIGNITY BAYVIEW100%35%0%0%
SHREE BHAIRAVNATH HEIGHTS100%90%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • DIGNITY BAYVIEW: covers 37 (Basement + Ground + 35 Upper Floors)
  • SHREE BHAIRAVNATH HEIGHTS: covers 26 (Basement + Ground + Mezzanine Floor + Service Floor + 22 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dignity Bayview every month.

Dignity Bayview: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK380 – 39563
2 BHK705 – 78558
3 BHK925 – 1,03158
Shops53 – 2506
Office Space170 – 5226
  • Buildings: DIGNITY BAYVIEW (15 floors, 116 units) · SHREE BHAIRAVNATH HEIGHTS (30 floors, 75 units)
  • Land: 2,391 sq m (about 0.6 acres) · sanctioned built-up 12,586 sq m · recreational space 191 sq m
  • Boundaries filed include: BANSIDHAR SCHOOL, SANYUKT EKJUT SOCIETY
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Dignity Bayview →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dignity Bayview: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Dignity Bayview

What is the possession date of Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Dignity Bayview in Wadala west, Mumbai is 31 July 2027 — 7 months later than 31 December 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Dignity Bayview?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dignity Bayview's builder has filed on MahaRERA, the official one, is 31 July 2027, already 7 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Dignity Bayview extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview's builder applied to MahaRERA to extend the completion date once: to 31 July 2027, giving the reason "The delay in completion of the Project is primarily attributable to the statutory process involved in obtaining the Environmental Clearance (EC), which was applied for on 30/06/2025 and granted by SEIAA, Maharashtra on 23/12/2025, resulting in a material impact on the Project execution schedule. Subsequently, procurement constraints, financial limitations, and site-specific execution challenges further affected the progress of the balance works; accordingly, we request an extension until 31/07/2027 to complete the Project and fulfil all applicable regulatory requirements.".

What is the RERA number of Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Dignity Bayview in Wadala west, Mumbai is P51900048008.

Is Dignity Bayview registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview is registered as P51900048008 and its status is "Registered and active".

What is the construction status of Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 35% to 90% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Dignity Bayview have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Dignity Bayview safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview is registered on MahaRERA as P51900048008, its completion date has moved 7 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Dignity Bayview's possession date changes?

The latest dates are on Dignity Bayview's MahaRERA page (P51900048008). GharKundli's Kundli Watch sends a free WhatsApp update on Dignity Bayview every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dignity Bayview have?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview has 2 buildings filed: DIGNITY BAYVIEW with 15 floors and 116 units; SHREE BHAIRAVNATH HEIGHTS with 30 floors and 75 units.

What are the flat sizes (carpet area) in Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Dignity Bayview: 1 BHK: 380 to 395 sq ft carpet (63 homes); 2 BHK: 705 to 785 sq ft carpet (58 homes); 3 BHK: 925 to 1031 sq ft carpet (58 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview stands on 2,391 sq m of land (about 0.6 acres), with 12,586 sq m of sanctioned built-up area and 191 sq m of recreational open space.

Where can I read reviews of Dignity Bayview?

Google Maps has reviews of Dignity Bayview written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Dignity Bayview?

Dignity Bayview by DIGNITY REALTY AND HOUSING is in Wadala west, Mumbai (pincode 400031), near Matunga, Dadar East, Hindu Colony, Maharashtra, and is registered on MahaRERA as P51900048008, per GharKundli's check of MahaRERA records. Its boundaries filed there include BANSIDHAR SCHOOL, SANYUKT EKJUT SOCIETY.

How many homes are in Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview has 179 homes in 2 towers registered on MahaRERA, and 58% of them are sold or booked.

When was Dignity Bayview registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dignity Bayview was registered on MahaRERA on 7 December 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Dignity Bayview?

1 court case is listed for Dignity Bayview on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Dignity Bayview?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DIGNITY REALTY AND HOUSING.

All projects with possession due in 2027 in Mumbai City →

Other projects in pincode 400031

All 26 projects in Wadala (400031) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.