by VIRTUOSO REALTY ENTERPRISES · Mira Road, Thane
Possession date of ANANTA: 30 April 2027, moved from 30 January 2025 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700019629, and currently active. Its completion date has moved from January 2025 to April 2027: 23 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANANTA?
How the possession date of ANANTA has moved
30 January 2025
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51700011830)
Reason the builder gave MahaRERA:
“we intend to extend the date of completion of project of residential portion due to (1) Pandemic of covid-19 and (2) Our Senior Partner SHRI MANHARLAL B. MEHTA (Owner of Maxus Mall, Bhayandar) died by Covid-19, hence we have stopped constru…” Read the full reason
“we intend to extend the date of completion of project of residential portion due to (1) Pandemic of covid-19 and (2) Our Senior Partner SHRI MANHARLAL B. MEHTA (Owner of Maxus Mall, Bhayandar) died by Covid-19, hence we have stopped construction of the said project during covid period.”31 December 2026
Extended at the builder's request (MahaRERA application EA26122519013)
Reason the builder gave MahaRERA:
“Since May 2025 heavy rains for 5 to 6 months and labour shortage disturbed the progress of construction work. We have completed 85% of the construction work of the Project. And balance finishing work is being carried out on the project and…” Read the full reason
“Since May 2025 heavy rains for 5 to 6 months and labour shortage disturbed the progress of construction work. We have completed 85% of the construction work of the Project. And balance finishing work is being carried out on the project and shall be completed on/or before 30/11/2026. We will apply and obtain Occupation Certificate from Mira Bhayander Municipal Corporation on/or Before 30/11/2026.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ANANTA’s extension records on MahaRERA (P51700019629), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANANTA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700019629
- Status
- Registered and active
- Builder
- VIRTUOSO REALTY ENTERPRISES
- Location
- Mira Road, Thane · 401107
- Project type
- Others
- Registered on
- 14 Feb 2019
- Completion date at registration
- January 2025
- Latest completion date
- April 2027
- Delay so far
- 23 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 196
- Sold or booked
- 49%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of ANANTA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANANTA | 100% | 90.32% | 65% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- ANANTA: covers 21 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANANTA every month.
ANANTA: buildings, flats and land, as filed on MahaRERA
- Buildings: ANANTA (24 floors, 232 units)
- Car parking: 88 covered
- Land: 1,499 sq m (about 0.4 acres) · sanctioned built-up 1,309 sq m
The builder’s record and reviews
Virtuoso Realty Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 5 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of ANANTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANANTA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANANTA
What is the possession date of ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANANTA in Mira Road, Thane is 30 April 2027 — 23 months later than 30 January 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ANANTA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANANTA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 23 months later than the 30 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANANTA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "we intend to extend the date of completion of project of residential portion due to (1) Pandemic of covid-19 and (2) Our Senior Partner SHRI MANHARLAL B. MEHTA (Owner of Maxus Mall, Bhayandar) died by Covid-19, hence we have stopped construction of the said project during covid period."; to 31 December 2026, giving the reason "Since May 2025 heavy rains for 5 to 6 months and labour shortage disturbed the progress of construction work. We have completed 85% of the construction work of the Project. And balance finishing work is being carried out on the project and shall be completed on/or before 30/11/2026. We will apply and obtain Occupation Certificate from Mira Bhayander Municipal Corporation on/or Before 30/11/2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANANTA in Mira Road, Thane is P51700019629.
Is ANANTA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA is registered as P51700019629 and its status is "Registered and active".
What is the construction status of ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANANTA is 90.32% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does ANANTA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANANTA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA is registered on MahaRERA as P51700019629, its completion date has moved 23 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANANTA's possession date changes?
The latest dates are on ANANTA's MahaRERA page (P51700019629). GharKundli's Kundli Watch sends a free WhatsApp update on ANANTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANANTA have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA has one building filed: ANANTA with 24 floors and 232 units.
How much parking does ANANTA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 88 covered car parking spaces for ANANTA.
How big is the land of ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA stands on 1,499 sq m of land (about 0.4 acres), with 1,309 sq m of sanctioned built-up area.
What is the track record of ANANTA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Virtuoso Realty Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 5 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ANANTA?
Google Maps has reviews of ANANTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANANTA?
ANANTA by VIRTUOSO REALTY ENTERPRISES is in Mira Road, Thane (pincode 401107), Maharashtra, and is registered on MahaRERA as P51700019629, per GharKundli's check of MahaRERA records.
How many homes are in ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA has 196 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.
When was ANANTA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA was registered on MahaRERA on 14 February 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on ANANTA?
No court cases are listed for ANANTA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ANANTA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIRTUOSO REALTY ENTERPRISES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ANANTA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 401107
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- RAJ CREST
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Other projects by VIRTUOSO REALTY ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.