ZUNERA HEIGHTS
by 786 MICRON BUILDERS & DEVELOPERS · Naya Nagar. Mira Road, Thane
Possession: ZUNERA HEIGHTS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020867. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ZUNERA HEIGHTS?
How the possession date of ZUNERA HEIGHTS has moved
30 December 2022
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700017435)
Reason the builder gave MahaRERA:
“Redevelopment work of Society was in process for possession and therefore project new building was on halt for completion that we restarted work for completion. Therefore we received consent from allottes for extension of project date as de…” Read the full reason
“Redevelopment work of Society was in process for possession and therefore project new building was on halt for completion that we restarted work for completion. Therefore we received consent from allottes for extension of project date as declared in extension date as mention above.”
Source: ZUNERA HEIGHTS’s extension records on MahaRERA (P51700020867), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ZUNERA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020867
- Status
- Completed
- Builder
- 786 MICRON BUILDERS & DEVELOPERS
- Location
- Naya Nagar. Mira Road, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 15 May 2019
- Completion date at registration
- December 2022
- Latest completion date
- December 2026
- Delay so far
- 48 months
- Homes
- 58
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ZUNERA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ZUNERA HEIGHTS 1 | 100% | 50% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ZUNERA HEIGHTS every month.
ZUNERA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: ZUNERA HEIGHTS 1 (15 floors)
- Land: 1,759 sq m (about 0.4 acres) · sanctioned built-up 2,159 sq m · recreational space 300 sq m
- Boundaries filed include: SHANTI NAGAR
The builder’s record and reviews
786 Micron Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 36 months). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of ZUNERA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ZUNERA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ZUNERA HEIGHTS
What is the possession date of ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ZUNERA HEIGHTS in Naya Nagar. Mira Road, Thane is 31 December 2026 — 48 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ZUNERA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ZUNERA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2026, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ZUNERA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Redevelopment work of Society was in process for possession and therefore project new building was on halt for completion that we restarted work for completion. Therefore we received consent from allottes for extension of project date as declared in extension date as mention above.".
What is the RERA number of ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ZUNERA HEIGHTS in Naya Nagar. Mira Road, Thane is P51700020867.
Is ZUNERA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS is registered as P51700020867 and its status is "Completed".
What is the construction status of ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on ZUNERA HEIGHTS 1 is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ZUNERA HEIGHTS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ZUNERA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS is registered on MahaRERA as P51700020867, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ZUNERA HEIGHTS's possession date changes?
The latest dates are on ZUNERA HEIGHTS's MahaRERA page (P51700020867). GharKundli's Kundli Watch sends a free WhatsApp update on ZUNERA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ZUNERA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS has one building filed: ZUNERA HEIGHTS 1 with 15 floors.
How big is the land of ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS stands on 1,759 sq m of land (about 0.4 acres), with 2,159 sq m of sanctioned built-up area and 300 sq m of recreational open space.
What is the track record of ZUNERA HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), 786 Micron Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 36 months). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ZUNERA HEIGHTS?
Google Maps has reviews of ZUNERA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ZUNERA HEIGHTS?
ZUNERA HEIGHTS by 786 MICRON BUILDERS & DEVELOPERS is in Naya Nagar. Mira Road, Thane (pincode 401107), Maharashtra, and is registered on MahaRERA as P51700020867, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHANTI NAGAR.
How many homes are in ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS has 58 homes in 1 tower registered on MahaRERA.
When was ZUNERA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ZUNERA HEIGHTS was registered on MahaRERA on 15 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on ZUNERA HEIGHTS?
No court cases are listed for ZUNERA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ZUNERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is 786 MICRON BUILDERS & DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of ZUNERA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401107
- Umiya Oasis
- PALM LANDS
- Sheetal Utsav
- JP CONNECT-MIRAROAD
- URBAN RESERVE WING B
- CHANDRESH TERRACE
- SHANTI SIGNATURE BY ASHIT SHAH
- LOTUS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.