Krishna Galaxy
by KRISHNA BUILDERS & DEVELOPERS · Varap, Thane 421301
What’s in the report? →Possession date of Krishna Galaxy (MahaRERA P51700020874): 31 December 2026, moved from 30 June 2023 (42 months later). It has 102 homes, 55% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020874, and currently active.
Source: MahaRERA website — records for P51700020874, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Krishna Galaxy?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Krishna Galaxy has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT51700016524)
Reason the builder gave MahaRERA:
“The project is under construction & we have completed majority of work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete…” Read the full reason
“The project is under construction & we have completed majority of work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 29/06/2024 for our Project.”29 December 2025
Extended at the builder's request (MahaRERA application EXT51700024326)
Reason the builder gave MahaRERA:
“The project is under construction & we have completed more than 90% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while reg…” Read the full reason
“The project is under construction & we have completed more than 90% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed.”31 December 2026
Extended at the builder's request (MahaRERA application EA16012619480)
Reason the builder gave MahaRERA:
“The project is under construction & we have completed more than 95% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while reg…” Read the full reason
“The project is under construction & we have completed more than 95% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed.”
Source: Krishna Galaxy’s extension records on MahaRERA (P51700020874), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Krishna Galaxy
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020874
- Status
- Registered and active
- Builder
- KRISHNA BUILDERS & DEVELOPERS
- Location
- Varap, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 15 May 2019
- Completion date at registration
- June 2023
- Latest completion date
- December 2026
- Delay so far
- 42 months
- Homes
- 102
- Sold or booked
- 55%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Krishna Galaxy, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 1 | 0% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING 1: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krishna Galaxy every 1–2 months.
Krishna Galaxy: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 1 (8 floors, 104 units)
- Land: 1,970 sq m (about 0.5 acres) · sanctioned built-up 1,968 sq m
- Land, as filed: SURVEY NO 42 HISSA NO 2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Krishna Galaxy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Krishna Galaxy: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Krishna Galaxy
What is the possession date of Krishna Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krishna Galaxy in Varap, Thane is 31 December 2026 — 42 months later than 30 June 2023, the date given at registration.
The date has already moved 42 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Krishna Galaxy?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Krishna Galaxy's builder has filed on MahaRERA, the official one, is 31 December 2026, already 42 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Krishna Galaxy extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2024, giving the reason "The project is under construction & we have completed majority of work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 29/06/2024 for our Project."; to 29 December 2025, giving the reason "The project is under construction & we have completed more than 90% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed."; to 31 December 2026, giving the reason "The project is under construction & we have completed more than 95% work on the project. However due to Scarcity of labours and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to above circumstances it is getting delayed.".
What is the RERA number of Krishna Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krishna Galaxy in Varap, Thane is P51700020874.
Is Krishna Galaxy registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy is registered as P51700020874 and its status is "Registered and active".
What is the current construction status of Krishna Galaxy? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Krishna Galaxy have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Krishna Galaxy safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy is registered on MahaRERA as P51700020874, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Krishna Galaxy?
Krishna Galaxy is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Krishna Galaxy?
For a flat in Krishna Galaxy (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Krishna Galaxy received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Krishna Galaxy uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Krishna Galaxy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Krishna Galaxy's possession date changes?
The latest dates are on Krishna Galaxy's MahaRERA page (P51700020874). GharKundli's Kundli Watch sends a free WhatsApp update on Krishna Galaxy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Krishna Galaxy have?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy has one building filed: BUILDING 1 with 8 floors and 104 units.
How big is the land of Krishna Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy stands on 1,970 sq m of land (about 0.5 acres), with 1,968 sq m of sanctioned built-up area.
What are the reviews of Krishna Galaxy?
Google Maps has reviews of Krishna Galaxy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Krishna Galaxy?
Krishna Galaxy by KRISHNA BUILDERS & DEVELOPERS is in Varap, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700020874, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 42 HISSA NO 2. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Krishna Galaxy, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy has 102 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.
When was Krishna Galaxy registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Galaxy was registered on MahaRERA on 15 May 2019. GharKundli did not find a title report on the land on file there.
Does Krishna Galaxy have any legal issues or court cases?
No court cases are listed for Krishna Galaxy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Krishna Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KRISHNA BUILDERS & DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Krishna Galaxy
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan (421301)
- Sadguru Krupa II Phase
- Vishwajeet Precious Phase V
- Krishna Empire 3
- Vishwajeet Precious Phase IV
- Saptshrungi Developers
- Vishwajeet Precious Phase I
- Vishwajeet Precious Phase III
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.