Sai Supreme
by SATISH MALANBAI ANDHARE · Dharmadhikari Plot, Solapur 413401
What’s in the report? →Possession date of Sai Supreme (MahaRERA P52600009202): 30 December 2020, moved from 1 July 2019 (17 months later), and it has already passed. It has 13 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600009202. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52600009202, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2020) has passed.
What do you want to know about Sai Supreme?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sai Supreme has moved
1 July 2019
Completion date given when the project was registered
30 June 2020
Extended at the builder's request (MahaRERA application EXT52600005543)
Reason the builder gave MahaRERA: “Delay due to unavailability of sand and building construction materials.”
30 December 2020
Revised completion date on MahaRERA
Source: Sai Supreme’s extension records on MahaRERA (P52600009202), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sai Supreme
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600009202
- Status
- Lapsed (registration period ended)
- Builder
- SATISH MALANBAI ANDHARE
- Location
- Dharmadhikari Plot, Solapur · 413401
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- July 2019
- Latest completion date
- December 2020
- Delay so far
- 17 months
- Homes
- 13
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Sai Supreme, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI SUPREME | 100% | 100% | 30% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Supreme every 1–2 months.
Sai Supreme: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI SUPREME (5 floors)
- Land: 406 sq m (about 0.1 acres) · sanctioned built-up 501 sq m
- Land, as filed: 725 1 73
- Map: Get directions
The builder’s record and reviews
Satish Malanbai Andhare has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Sai Supreme →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sai Supreme: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sai Supreme
What is the possession date of Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Supreme in Dharmadhikari Plot, Solapur is 30 December 2020 — 17 months later than 1 July 2019, the date given at registration. That date has already passed.
The date has already moved 17 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sai Supreme?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Supreme's builder has filed on MahaRERA, the official one, is 30 December 2020, already 17 months later than the 1 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sai Supreme extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme's builder applied to MahaRERA to extend the completion date once: to 30 June 2020, giving the reason "Delay due to unavailability of sand and building construction materials.".
What is the RERA number of Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Supreme in Dharmadhikari Plot, Solapur is P52600009202.
Is Sai Supreme registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme is registered as P52600009202 and its status is "Lapsed (registration period ended)".
What is the current construction status of Sai Supreme? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI SUPREME is 100% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does Sai Supreme have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Sai Supreme safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme is registered on MahaRERA as P52600009202, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sai Supreme?
Sai Supreme isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sai Supreme?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sai Supreme: gharkundli.com/tools/property-cost-calculator
Has Sai Supreme received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Sai Supreme uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sai Supreme was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sai Supreme's possession date changes?
The latest dates are on Sai Supreme's MahaRERA page (P52600009202). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Supreme every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sai Supreme have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme has one building filed: SAI SUPREME with 5 floors.
How big is the land of Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme stands on 406 sq m of land (about 0.1 acres), with 501 sq m of sanctioned built-up area.
What is the track record of Sai Supreme's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Satish Malanbai Andhare has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sai Supreme?
Google Maps has reviews of Sai Supreme written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sai Supreme?
Sai Supreme by SATISH MALANBAI ANDHARE is in Dharmadhikari Plot, Solapur, pincode 413401, Maharashtra, and is registered on MahaRERA as P52600009202, per GharKundli's check of MahaRERA records. Its land is filed as 725 1 73. GharKundli lists all 26 MahaRERA projects in Barshi (413401).
How many flats are in Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme has 13 homes in 1 tower registered on MahaRERA.
When was Sai Supreme registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sai Supreme was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Does Sai Supreme have any legal issues or court cases?
No court cases are listed for Sai Supreme on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Sai Supreme?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SATISH MALANBAI ANDHARE, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sai Supreme
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Barshi
- Sai Palacio
- Kathale Vihar
- Pmay Barshi Nagar Parishad Ahp
- Royal Residency Building No 4
- Sukhdev Nagar Phase 2
- Soham Heights
- Jagnnath Puram Phase I
- Samruddhi Apartment
Other projects by SATISH MALANBAI ANDHARE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.