INDRADHANU-Phase-2
by M/S Ganesh Ramchandra Apte · Laxmi Peth, Solapur
Possession date of INDRADHANU-Phase-2: 31 July 2029, moved from 31 July 2023 (68 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600006002, and currently active. Its completion date has moved from July 2023 to July 2029: 68 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about INDRADHANU-Phase-2?
How the possession date of INDRADHANU-Phase-2 has moved
31 July 2023
Completion date given when the project was registered
31 March 2029
Extended at the builder's request (MahaRERA application EXT52600025312)
Reason the builder gave MahaRERA: “due to Covid the initial phase of building was slowed down because of that construction progress got delayed. therefore we are requesting you to consider our request for extension of application please do needful”
31 July 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: INDRADHANU-Phase-2’s extension records on MahaRERA (P52600006002), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on INDRADHANU-Phase-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- INDRADHANU Phase-3P52600009419
- INDRADHANU-Phase-5P52600015861 · possession 31 Dec 2035
- INDRADHANU-Phase-6P52600028752
- INDRADHANU-Phase-7P52600028720
- INDRADHANU-Phase-8P52600031941
- INDRADHANU-Phase-IVP52600014920 · possession 31 Dec 2028
- MahaRERA registration
- P52600006002
- Status
- Registered and active
- Builder
- M/S Ganesh Ramchandra Apte
- Location
- Laxmi Peth, Solapur · 413001
- Project type
- Others
- Registered on
- 14 Aug 2017
- Completion date at registration
- July 2023
- Latest completion date
- July 2029
- Delay so far
- 68 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 10%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of INDRADHANU-Phase-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing Z | 0% | 100% | 99% | 98% |
Commencement certificate (CC), as filed on MahaRERA
- Wing Z: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on INDRADHANU-Phase-2 every month.
INDRADHANU-Phase-2: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing Z (5 floors, 29 units)
- Car parking: 10 covered
- Land: 1,206 sq m (about 0.3 acres) · sanctioned built-up 1,736 sq m
The builder’s record and reviews
Ganesh Ramchandra Apte has 8 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 3 still being built, 1 past the promised date (typically 23 months late). No complaints on MahaRERA.
Read Google reviews of INDRADHANU-Phase-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
INDRADHANU-Phase-2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about INDRADHANU-Phase-2
What is the possession date of INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for INDRADHANU-Phase-2 in Laxmi Peth, Solapur is 31 July 2029 — 68 months later than 31 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for INDRADHANU-Phase-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date INDRADHANU-Phase-2's builder has filed on MahaRERA, the official one, is 31 July 2029, already 68 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of INDRADHANU-Phase-2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2's builder applied to MahaRERA to extend the completion date once: to 31 March 2029, giving the reason "due to Covid the initial phase of building was slowed down because of that construction progress got delayed. therefore we are requesting you to consider our request for extension of application please do needful". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of INDRADHANU-Phase-2 in Laxmi Peth, Solapur is P52600006002.
Is INDRADHANU-Phase-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 is registered as P52600006002 and its status is "Registered and active".
What is the construction status of INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing Z is 100% done and internal work 99%. GharKundli's full report compares construction progress with the deadline.
Does INDRADHANU-Phase-2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is INDRADHANU-Phase-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 is registered on MahaRERA as P52600006002, its completion date has moved 68 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does INDRADHANU-Phase-2 have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: INDRADHANU Phase-3 (P52600009419); INDRADHANU-Phase-5 (P52600015861, possession 31 Dec 2035); INDRADHANU-Phase-6 (P52600028752); INDRADHANU-Phase-7 (P52600028720); INDRADHANU-Phase-8 (P52600031941); INDRADHANU-Phase-IV (P52600014920, possession 31 Dec 2028). Check that your agreement names the registration of your own wing.
How can I get updates if INDRADHANU-Phase-2's possession date changes?
The latest dates are on INDRADHANU-Phase-2's MahaRERA page (P52600006002). GharKundli's Kundli Watch sends a free WhatsApp update on INDRADHANU-Phase-2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does INDRADHANU-Phase-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 has one building filed: Wing Z with 5 floors and 29 units.
How much parking does INDRADHANU-Phase-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for INDRADHANU-Phase-2.
How big is the land of INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 stands on 1,206 sq m of land (about 0.3 acres), with 1,736 sq m of sanctioned built-up area.
What is the track record of INDRADHANU-Phase-2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganesh Ramchandra Apte has 8 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 3 still being built, 1 past the promised date (typically 23 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of INDRADHANU-Phase-2?
Google Maps has reviews of INDRADHANU-Phase-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is INDRADHANU-Phase-2?
INDRADHANU-Phase-2 by M/S Ganesh Ramchandra Apte is in Laxmi Peth, Solapur (pincode 413001), Maharashtra, and is registered on MahaRERA as P52600006002, per GharKundli's check of MahaRERA records.
How many homes are in INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 has 0 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.
When was INDRADHANU-Phase-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INDRADHANU-Phase-2 was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on INDRADHANU-Phase-2?
No court cases are listed for INDRADHANU-Phase-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of INDRADHANU-Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S Ganesh Ramchandra Apte, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of INDRADHANU-Phase-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Solapur →
Other projects in Solapur North
- INDRADHANU-Phase-IV
- Platinum Mall
- INDRADHANU-Phase-5
- Kaizen Emerald
- SAMARTH PRASAD
- Shivtej Plaza
- VIJAYS THE PRESTIGE
- F.F AMORA
Other projects by M/S Ganesh Ramchandra Apte
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.