F.F AMORA
by F F CITY TOWER DEVELOPERS · Siddeshwar Peth, Solapur
Possession date of F.F AMORA: 30 October 2027, moved from 20 December 2020 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600013502, and currently active. Its completion date has moved from December 2020 to October 2027: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about F.F AMORA?
How the possession date of F.F AMORA has moved
20 December 2020
Completion date given when the project was registered
31 October 2023
Extended at the builder's request (MahaRERA application EXT52600011046)
Reason the builder gave MahaRERA: “Dear Sir, Due to certain site conditions project was delayed. But as of now the project is completed 95%. We have received consent of 100% of allotteees. Please kindly allow us extension.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT52600018936)
Reason the builder gave MahaRERA:
“Subject: Application for extension to the project bearing registration number P52600013502. Sir, We, FF City Tower Developers, hereby apply for extension u/s 7(3) of the registered project bearing vide no P52600013502. As prescribed under c…” Read the full reason
“Subject: Application for extension to the project bearing registration number P52600013502. Sir, We, FF City Tower Developers, hereby apply for extension u/s 7(3) of the registered project bearing vide no P52600013502. As prescribed under circular no 07/2019 dated 08 Feb 2019, the consent of 51% of the allottees is enclosed herewith.”30 June 2027
Extended at the builder's request (MahaRERA application EA31122519180)
Reason the builder gave MahaRERA:
“We, F F City Tower Developers, are promoter of the project F.F Amora, registered under MahaRERA vide registration number P52600013502. Sir the foresaid project was projected to be completed by 20/12/2020 but due to lesser response in bookin…” Read the full reason
“We, F F City Tower Developers, are promoter of the project F.F Amora, registered under MahaRERA vide registration number P52600013502. Sir the foresaid project was projected to be completed by 20/12/2020 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 100% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 68 units in the project, we have sold 68 units. Out of which 43 have already given their consent for extension o…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: F.F AMORA’s extension records on MahaRERA (P52600013502), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on F.F AMORA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600013502
- Status
- Registered and active
- Builder
- F F CITY TOWER DEVELOPERS
- Location
- Siddeshwar Peth, Solapur · 413003
- Project type
- Residential / Group Housing
- Registered on
- 9 Oct 2017
- Completion date at registration
- December 2020
- Latest completion date
- October 2027
- Delay so far
- 78 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of F.F AMORA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AMORA | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- AMORA: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on F.F AMORA every month.
F.F AMORA: buildings, flats and land, as filed on MahaRERA
- Buildings: AMORA (8 floors, 68 units)
- Land: 2,338 sq m (about 0.6 acres) · sanctioned built-up 2,153 sq m · recreational space 1,500 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of F.F AMORA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
F.F AMORA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about F.F AMORA
What is the possession date of F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for F.F AMORA in Siddeshwar Peth, Solapur is 30 October 2027 — 78 months later than 20 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for F.F AMORA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date F.F AMORA's builder has filed on MahaRERA, the official one, is 30 October 2027, already 78 months later than the 20 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of F.F AMORA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA's builder applied to MahaRERA to extend the completion date 3 times: to 31 October 2023, giving the reason "Dear Sir, Due to certain site conditions project was delayed. But as of now the project is completed 95%. We have received consent of 100% of allotteees. Please kindly allow us extension."; to 31 December 2025, giving the reason "Subject: Application for extension to the project bearing registration number P52600013502. Sir, We, FF City Tower Developers, hereby apply for extension u/s 7(3) of the registered project bearing vide no P52600013502. As prescribed under circular no 07/2019 dated 08 Feb 2019, the consent of 51% of the allottees is enclosed herewith."; to 30 June 2027, giving the reason "We, F F City Tower Developers, are promoter of the project F.F Amora, registered under MahaRERA vide registration number P52600013502. Sir the foresaid project was projected to be completed by 20/12/2020 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 100% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 68 units in the project, we have sold 68 units. Out of which 43 have already given their consent for extension o…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of F.F AMORA in Siddeshwar Peth, Solapur is P52600013502.
Is F.F AMORA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA is registered as P52600013502 and its status is "Registered and active".
What is the construction status of F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AMORA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does F.F AMORA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is F.F AMORA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA is registered on MahaRERA as P52600013502, its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if F.F AMORA's possession date changes?
The latest dates are on F.F AMORA's MahaRERA page (P52600013502). GharKundli's Kundli Watch sends a free WhatsApp update on F.F AMORA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does F.F AMORA have?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA has one building filed: AMORA with 8 floors and 68 units.
How big is the land of F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA stands on 2,338 sq m of land (about 0.6 acres), with 2,153 sq m of sanctioned built-up area and 1,500 sq m of recreational open space.
Where can I read reviews of F.F AMORA?
Google Maps has reviews of F.F AMORA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is F.F AMORA?
F.F AMORA by F F CITY TOWER DEVELOPERS is in Siddeshwar Peth, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600013502, per GharKundli's check of MahaRERA records.
How many homes are in F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA has 68 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was F.F AMORA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), F.F AMORA was registered on MahaRERA on 9 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on F.F AMORA?
No court cases are listed for F.F AMORA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of F.F AMORA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is F F CITY TOWER DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of F.F AMORA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Solapur →
Other projects in Solapur North
- Kaizen Emerald
- SAMARTH PRASAD
- VIJAYS THE PRESTIGE
- Shivtej Plaza
- PRAJAY HEIGHTS
- Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha
- SHHRADDHA AVENUE
- Balaji Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.