Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha

by Anukarati Homes Private Limited · Solapur North, Solapur

Possession date of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600076701, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA09012619369)

    Reason the builder gave MahaRERA:
    “Respected Sir, Here we are declaring the reasons for delay of the project: 1) Beneficiary verification process: As the project is approved under PMAY (U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS cate…” Read the full reason“Respected Sir, Here we are declaring the reasons for delay of the project: 1) Beneficiary verification process: As the project is approved under PMAY (U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS category as per PMAY guidelines by Solapur Municipal Corporation, CLTC Cell and has to be registered on PMAY portal ultimately generating a beneficiary code. The process of documentation took time, resulting in slow progress of work in need of beneficiary contribution. Submission & approval of beneficiary code as shown in below table: List No. No. of Benefici…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA24062621500)

    Reason the builder gave MahaRERA:
    “As the project is approved under PMAY(U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS category as per PMAY guidelines by Solapur Municipal Corporation, CLTC Cell and has to be registered on PMAY portal u…” Read the full reason“As the project is approved under PMAY(U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS category as per PMAY guidelines by Solapur Municipal Corporation, CLTC Cell and has to be registered on PMAY portal ultimately generating a beneficiary code. The process of documentation took time. Resulting in slow progress of work in need of beneficiary contribution. After generation of beneficiary code, these EWS approved beneficiaries submit their files to banks for housing loan approval as they have to finance home purchase due to their current economic condition.…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha’s extension records on MahaRERA (P52600076701), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600076701
Status
Registered and active
Builder
Anukarati Homes Private Limited
Location
Solapur North, Solapur · 413005
Project type
Residential / Group Housing
Registered on
21 Jun 2024
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
288
Sold or booked
76%
Towers
9
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A1100%100%100%100%
A2100%100%100%100%
A3100%100%100%100%
A4100%100%100%100%
A5100%100%100%100%
A6100%100%100%100%
A7100%100%100%100%
A8100%100%100%100%
A9100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • A1: covers 4 floors
  • A2: covers 4 floors
  • A3: covers 4 floors
  • A4: covers 4 floors
  • A5: covers 4 floors
  • A6: covers 4 floors
  • A7: covers 4 floors
  • A8: covers 4 floors
  • A9: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha every month.

Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha: buildings, flats and land, as filed on MahaRERA

  • Buildings: A1 (4 floors, 32 units) · A2 (4 floors, 32 units) · A3 (4 floors, 32 units) · A4 (4 floors, 32 units) · A5 (4 floors, 32 units) · A6 (4 floors, 32 units) · A7 (4 floors, 32 units) · A8 (4 floors, 32 units) · and 1 more
  • Land: 16,920 sq m (about 4.2 acres) · sanctioned built-up 10,944 sq m · recreational space 1,796 sq m

The builder’s record and reviews

Ajan Homes has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha

What is the possession date of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha in Solapur North, Solapur is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Respected Sir, Here we are declaring the reasons for delay of the project: 1) Beneficiary verification process: As the project is approved under PMAY (U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS category as per PMAY guidelines by Solapur Municipal Corporation, CLTC Cell and has to be registered on PMAY portal ultimately generating a beneficiary code. The process of documentation took time, resulting in slow progress of work in need of beneficiary contribution. Submission & approval of beneficiary code as shown in below table: List No. No. of Benefici…"; to 31 December 2026, giving the reason "As the project is approved under PMAY(U)-1 and is aimed for EWS of the society, the beneficiary has to be verified for EWS category as per PMAY guidelines by Solapur Municipal Corporation, CLTC Cell and has to be registered on PMAY portal ultimately generating a beneficiary code. The process of documentation took time. Resulting in slow progress of work in need of beneficiary contribution. After generation of beneficiary code, these EWS approved beneficiaries submit their files to banks for housing loan approval as they have to finance home purchase due to their current economic condition.…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha in Solapur North, Solapur is P52600076701.

Is Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha is registered as P52600076701 and its status is "Registered and active".

What is the construction status of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 9 towers. GharKundli's full report compares construction progress with the deadline.

Does Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha is registered on MahaRERA as P52600076701, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's possession date changes?

The latest dates are on Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's MahaRERA page (P52600076701). GharKundli's Kundli Watch sends a free WhatsApp update on Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha have?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha has 9 buildings filed: A1 with 4 floors and 32 units; A2 with 4 floors and 32 units; A3 with 4 floors and 32 units; A4 with 4 floors and 32 units; A5 with 4 floors and 32 units; A6 with 4 floors and 32 units; and 3 more.

How big is the land of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha stands on 16,920 sq m of land (about 4.2 acres), with 10,944 sq m of sanctioned built-up area and 1,796 sq m of recreational open space.

What is the track record of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ajan Homes has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

Google Maps has reviews of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha by Anukarati Homes Private Limited is in Solapur North, Solapur (pincode 413005), Maharashtra, and is registered on MahaRERA as P52600076701, per GharKundli's check of MahaRERA records.

How many homes are in Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha has 288 homes in 9 towers registered on MahaRERA, and 76% of them are sold or booked.

When was Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha was registered on MahaRERA on 21 June 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

No court cases are listed for Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Anukarati Homes Private Limited.

All projects with possession due in 2027 in Solapur →

Other projects in Solapur North

All 30 projects in Daji Peth (413005) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.