Possession date of SHHRADDHA AVENUE: 30 October 2027, moved from 31 May 2026 (13 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600050680, and currently active. Its completion date has moved from May 2026 to October 2027: 13 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHHRADDHA AVENUE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHHRADDHA AVENUE has moved

  1. 31 May 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA06052620849)

    Reason the builder gave MahaRERA: “Slow Response from customer”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHHRADDHA AVENUE’s extension records on MahaRERA (P52600050680), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHHRADDHA AVENUE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600050680
Status
Registered and active
Builder
SHRADDHA ENTERPRISES
Location
Near Sbi Colony, Solapur · 413002
Project type
Residential / Group Housing
Registered on
28 Apr 2023
Completion date at registration
May 2026
Latest completion date
October 2027
Delay so far
13 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Sold or booked
72%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SHHRADDHA AVENUE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHHRADDHA AVENUE100%100%80%70%

Commencement certificate (CC), as filed on MahaRERA

  • SHHRADDHA AVENUE: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHHRADDHA AVENUE every month.

SHHRADDHA AVENUE: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHHRADDHA AVENUE (8 floors, 29 units)
  • Car parking: 11 open
  • Land: 606 sq m (about 0.1 acres) · sanctioned built-up 2,233 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHHRADDHA AVENUE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHHRADDHA AVENUE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHHRADDHA AVENUE

What is the possession date of SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHHRADDHA AVENUE in Near Sbi Colony, Solapur is 30 October 2027 — 13 months later than 31 May 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHHRADDHA AVENUE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHHRADDHA AVENUE's builder has filed on MahaRERA, the official one, is 30 October 2027, already 13 months later than the 31 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHHRADDHA AVENUE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "Slow Response from customer". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHHRADDHA AVENUE in Near Sbi Colony, Solapur is P52600050680.

Is SHHRADDHA AVENUE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE is registered as P52600050680 and its status is "Registered and active".

What is the construction status of SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHHRADDHA AVENUE is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does SHHRADDHA AVENUE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHHRADDHA AVENUE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE is registered on MahaRERA as P52600050680, its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHHRADDHA AVENUE's possession date changes?

The latest dates are on SHHRADDHA AVENUE's MahaRERA page (P52600050680). GharKundli's Kundli Watch sends a free WhatsApp update on SHHRADDHA AVENUE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHHRADDHA AVENUE have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE has one building filed: SHHRADDHA AVENUE with 8 floors and 29 units.

How much parking does SHHRADDHA AVENUE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 11 open car parking spaces for SHHRADDHA AVENUE.

How big is the land of SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE stands on 606 sq m of land (about 0.1 acres), with 2,233 sq m of sanctioned built-up area.

Where can I read reviews of SHHRADDHA AVENUE?

Google Maps has reviews of SHHRADDHA AVENUE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHHRADDHA AVENUE?

SHHRADDHA AVENUE by SHRADDHA ENTERPRISES is in Near Sbi Colony, Solapur (pincode 413002), Maharashtra, and is registered on MahaRERA as P52600050680, per GharKundli's check of MahaRERA records.

How many homes are in SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE has 29 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was SHHRADDHA AVENUE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHHRADDHA AVENUE was registered on MahaRERA on 28 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SHHRADDHA AVENUE?

No court cases are listed for SHHRADDHA AVENUE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHHRADDHA AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRADDHA ENTERPRISES, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Solapur →

Other projects in Solapur North

All 25 projects in Budhwar Peth (413002) →

Other projects by SHRADDHA ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.