by Bhalchandra Wadnerkar · Shastri Nagar, ThaneAlso near Dombivli West, Ramnagar, Ram Nagar

Possession date of SAI DATTA KRIPA: 30 April 2028, moved from 30 June 2023 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700027824, and currently active. Its completion date has moved from June 2023 to April 2028: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI DATTA KRIPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI DATTA KRIPA has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51700025788)

    Reason the builder gave MahaRERA: “The project is completed on time but the Collector NOC has been delayed due to interpretation of the new GR.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAI DATTA KRIPA’s extension records on MahaRERA (P51700027824), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI DATTA KRIPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700027824
Status
Registered and active
Builder
Bhalchandra Wadnerkar
Location
Shastri Nagar, Thane · 421202
Project type
Others
Registered on
4 Jan 2021
Completion date at registration
June 2023
Latest completion date
April 2028
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Sold or booked
82%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of SAI DATTA KRIPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI DATTA KRIPA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SAI DATTA KRIPA: covers Stilt+Ground+5 Habitable Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI DATTA KRIPA every month.

SAI DATTA KRIPA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Bhalchandra Vinayak Wadnerkar has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 102 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SAI DATTA KRIPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI DATTA KRIPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI DATTA KRIPA

What is the possession date of SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI DATTA KRIPA in Shastri Nagar, Thane is 30 April 2028 — 54 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAI DATTA KRIPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI DATTA KRIPA's builder has filed on MahaRERA, the official one, is 30 April 2028, already 54 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI DATTA KRIPA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The project is completed on time but the Collector NOC has been delayed due to interpretation of the new GR.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI DATTA KRIPA in Shastri Nagar, Thane is P51700027824.

Is SAI DATTA KRIPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA is registered as P51700027824 and its status is "Registered and active".

What is the construction status of SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DATTA KRIPA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI DATTA KRIPA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI DATTA KRIPA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA is registered on MahaRERA as P51700027824, its completion date has moved 54 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI DATTA KRIPA's possession date changes?

The latest dates are on SAI DATTA KRIPA's MahaRERA page (P51700027824). GharKundli's Kundli Watch sends a free WhatsApp update on SAI DATTA KRIPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI DATTA KRIPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA has one building filed: SAI DATTA KRIPA with 10 floors and 28 units.

How much parking does SAI DATTA KRIPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 covered car parking spaces for SAI DATTA KRIPA.

How big is the land of SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA stands on 736 sq m of land (about 0.2 acres).

What is the track record of SAI DATTA KRIPA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Bhalchandra Vinayak Wadnerkar has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 5 finished, all within the promised date; 4 still being built, 3 past the promised date (typically 102 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI DATTA KRIPA?

Google Maps has reviews of SAI DATTA KRIPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI DATTA KRIPA?

SAI DATTA KRIPA by Bhalchandra Wadnerkar is in Shastri Nagar, Thane (pincode 421202), near Dombivli West, Ramnagar, Ram Nagar, Maharashtra, and is registered on MahaRERA as P51700027824, per GharKundli's check of MahaRERA records.

How many homes are in SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA has 20 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.

When was SAI DATTA KRIPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DATTA KRIPA was registered on MahaRERA on 4 January 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI DATTA KRIPA?

No court cases are listed for SAI DATTA KRIPA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAI DATTA KRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bhalchandra Wadnerkar, which has 7 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Shastri Nagar

All 226 projects in Vishnunagar (421202) →

Other projects by Bhalchandra Wadnerkar

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.