Shindeshahi Residency
by Maruti Narayan Shinde · Near Shakuntalnagar, Solapur
Possession: Shindeshahi Residency is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600023067. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Shindeshahi Residency?
How the possession date of Shindeshahi Residency has moved
30 May 2022
Completion date given when the project was registered
29 May 2023
Extended at the builder's request (MahaRERA application EXT52600012385)
Reason the builder gave MahaRERA:
“(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Du…” Read the full reason
“(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to Corporation completion certificate.”
Source: Shindeshahi Residency’s extension records on MahaRERA (P52600023067), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shindeshahi Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600023067
- Status
- Completed
- Builder
- Maruti Narayan Shinde
- Location
- Near Shakuntalnagar, Solapur · 413304
- Project type
- Residential / Group Housing
- Registered on
- 22 Nov 2019
- Completion date at registration
- May 2022
- Latest completion date
- May 2023
- Delay so far
- 12 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shindeshahi Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shindeshahi Residency every month.
Shindeshahi Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (6 floors)
- Land: 1,400 sq m (about 0.3 acres) · sanctioned built-up 1,351 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shindeshahi Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shindeshahi Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shindeshahi Residency
What is the possession date of Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shindeshahi Residency in Near Shakuntalnagar, Solapur is 29 May 2023 — 12 months later than 30 May 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shindeshahi Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shindeshahi Residency's builder has filed on MahaRERA, the official one, is 29 May 2023, already 12 months later than the 30 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shindeshahi Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency's builder applied to MahaRERA to extend the completion date once: to 29 May 2023, giving the reason "(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to Corporation completion certificate.".
What is the RERA number of Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shindeshahi Residency in Near Shakuntalnagar, Solapur is P52600023067.
Is Shindeshahi Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency is registered as P52600023067 and its status is "Completed".
What is the construction status of Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency's status on MahaRERA is "Completed". As filed by the builder, slab work on BUILDING A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shindeshahi Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shindeshahi Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency is registered on MahaRERA as P52600023067, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shindeshahi Residency's possession date changes?
The latest dates are on Shindeshahi Residency's MahaRERA page (P52600023067). GharKundli's Kundli Watch sends a free WhatsApp update on Shindeshahi Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shindeshahi Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency has one building filed: BUILDING A with 6 floors.
How big is the land of Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency stands on 1,400 sq m of land (about 0.3 acres), with 1,351 sq m of sanctioned built-up area.
Where can I read reviews of Shindeshahi Residency?
Google Maps has reviews of Shindeshahi Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shindeshahi Residency?
Shindeshahi Residency by Maruti Narayan Shinde is in Near Shakuntalnagar, Solapur (pincode 413304), Maharashtra, and is registered on MahaRERA as P52600023067, per GharKundli's check of MahaRERA records.
How many homes are in Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency has 28 homes in 1 tower registered on MahaRERA.
When was Shindeshahi Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shindeshahi Residency was registered on MahaRERA on 22 November 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Shindeshahi Residency?
No court cases are listed for Shindeshahi Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Shindeshahi Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Maruti Narayan Shinde.
Check it yourself on MahaRERA
- How to check the possession date of Shindeshahi Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pandharpur
- Kandre Residency
- Aarambha Residency
- STAR AVENEU
- Tirupati Harisha
- HARISAMARTH RESIDENCY
- Kandre's Residency Building No.B2
- KANDRES RESIDENCY A5 BUILDING
- BLOSSOM PARK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.