by Heritage Ashcon Properties · MIDC Solapur, SolapurAlso near Shivshahi

Possession date of Heritage Prime phase 3: 1 June 2023. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52600046751. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2023) has passed.

What do you want to know about Heritage Prime phase 3?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Heritage Prime phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52600046751
Status
Lapsed (registration period ended)
Builder
Heritage Ashcon Properties
Location
MIDC Solapur, Solapur · 413006
Project type
Plotted
Registered on
5 Sep 2022
Completion date at registration
June 2023
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Heritage Prime phase 3: buildings, flats and land, as filed on MahaRERA

  • Land: 5,599 sq m (about 1.4 acres) · sanctioned built-up 4,877 sq m · recreational space 722 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Heritage Prime phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Heritage Prime phase 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Heritage Prime phase 3

What is the possession date of Heritage Prime phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Heritage Prime phase 3 in MIDC Solapur, Solapur is 1 June 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Heritage Prime phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Heritage Prime phase 3's builder has filed on MahaRERA, the official one, is 1 June 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Heritage Prime phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Heritage Prime phase 3 in MIDC Solapur, Solapur is P52600046751.

Is Heritage Prime phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Heritage Prime phase 3 is registered as P52600046751 and its status is "Lapsed (registration period ended)".

What is the construction status of Heritage Prime phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Heritage Prime phase 3's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does Heritage Prime phase 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Heritage Prime phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Heritage Prime phase 3 is registered on MahaRERA as P52600046751, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Heritage Prime phase 3 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Heritage Prime (P52600032341); Heritage Prime Phase 2 (P52600046806). Check that your agreement names the registration of your own wing.

How can I get updates if Heritage Prime phase 3's possession date changes?

The latest dates are on Heritage Prime phase 3's MahaRERA page (P52600046751). GharKundli's Kundli Watch sends a free WhatsApp update on Heritage Prime phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Heritage Prime phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Heritage Prime phase 3 stands on 5,599 sq m of land (about 1.4 acres), with 4,877 sq m of sanctioned built-up area and 722 sq m of recreational open space.

Where can I read reviews of Heritage Prime phase 3?

Google Maps has reviews of Heritage Prime phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Heritage Prime phase 3?

Heritage Prime phase 3 by Heritage Ashcon Properties is in MIDC Solapur, Solapur (pincode 413006), near Shivshahi, Maharashtra, and is registered on MahaRERA as P52600046751, per GharKundli's check of MahaRERA records.

When was Heritage Prime phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Heritage Prime phase 3 was registered on MahaRERA on 5 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Heritage Prime phase 3?

No court cases are listed for Heritage Prime phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Heritage Prime phase 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Heritage Ashcon Properties, which has 2 other projects registered on MahaRERA.

Other projects in Solapur North

Other projects by Heritage Ashcon Properties

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.