Skip to content
GharKundli

Kotkunde Crown

by Murtuz Abdul Razzaque Kotkunde · Majrewadi, Solapur

Possession date of Kotkunde Crown: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600051608, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Kotkunde Crown?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kotkunde Crown has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kotkunde Crown’s extension records on MahaRERA (P52600051608), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kotkunde Crown

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600051608
Status
Registered and active
Builder
Murtuz Abdul Razzaque Kotkunde
Location
Majrewadi, Solapur · 413003
Project type
Residential / Group Housing
Registered on
27 Jun 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Kotkunde Crown, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Kotkunde Crown0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kotkunde Crown every month.

Kotkunde Crown: buildings, flats and land, as filed on MahaRERA

  • Buildings: Kotkunde Crown (8 floors)
  • Land: 604 sq m (about 0.1 acres) · sanctioned built-up 2,597 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Kotkunde Crown →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kotkunde Crown: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kotkunde Crown

What is the possession date of Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kotkunde Crown in Majrewadi, Solapur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kotkunde Crown?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kotkunde Crown's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kotkunde Crown in Majrewadi, Solapur is P52600051608.

Is Kotkunde Crown registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown is registered as P52600051608 and its status is "Registered and active".

What is the construction status of Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kotkunde Crown is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Kotkunde Crown have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kotkunde Crown safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown is registered on MahaRERA as P52600051608, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Kotkunde Crown's possession date changes?

The latest dates are on Kotkunde Crown's MahaRERA page (P52600051608). GharKundli's Kundli Watch sends a free WhatsApp update on Kotkunde Crown every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kotkunde Crown have?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown has one building filed: Kotkunde Crown with 8 floors.

How big is the land of Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown stands on 604 sq m of land (about 0.1 acres), with 2,597 sq m of sanctioned built-up area.

Where can I read reviews of Kotkunde Crown?

Google Maps has reviews of Kotkunde Crown written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kotkunde Crown?

Kotkunde Crown by Murtuz Abdul Razzaque Kotkunde is in Majrewadi, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600051608, per GharKundli's check of MahaRERA records.

How many homes are in Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown has 30 homes in 1 tower registered on MahaRERA.

When was Kotkunde Crown registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kotkunde Crown was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Kotkunde Crown?

No court cases are listed for Kotkunde Crown on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Kotkunde Crown?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Murtuz Abdul Razzaque Kotkunde, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Solapur →

Other projects in Majrewadi

All 28 projects in Majrewadi (413003) →

Other projects by Murtuz Abdul Razzaque Kotkunde

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.