MahaRERA projects in Gurunanak Nagar, Solapur (413003)
According to GharKundli's check of MahaRERA records, 31 housing projects are registered in pincode 413003 (Gurunanak Nagar, Solapur). 19 are still being built, 9 with possession due by the end of 2027. For 22, the completion date on MahaRERA is later than the one first promised. 1 has at least one complaint filed on MahaRERA.
Pincode 413003 also covers: Majrewadi, Antrolikar Nagar, Solapur.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| JayPrakash Heights Vijay Constructions | Active | 31 Dec 2026 | 20 Aug 2025 | 0 |
| Swami Samarth Regency Shri Swami Samarth Developers | Active | 31 Dec 2026 | same | 0 |
| Aastha Residency Nitin Hukumchand Rathod | Active | 30 Apr 2027 | 1 Jun 2025 | 0 |
| City Center Tower City Centre Developers | Active | 30 Apr 2027 | 15 Jun 2022 | 0 |
| Kotkunde Crown Murtuz Abdul Razzaque Kotkunde | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Nilayam Heights Sachin Purushottam Kulkarni | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Skyline Springs Skyline builders & Developers | Active | 1 May 2027 | 1 Jan 2027 | 0 |
| FLORA KALPANA IMAGE SPACE INCORPORATED | Active | 30 Aug 2027 | 30 Apr 2027 | 0 |
| F.F AMORA F F CITY TOWER DEVELOPERS | Active | 30 Oct 2027 | 20 Dec 2020 | 0 |
| Aakruti Heritage Aakruti Developers | Active | 1 Mar 2028 | 1 Nov 2027 | 0 |
| Deepgiri Heights Sachin Purushottam Kulkarni | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Laxmi Residency Laxmikant Infra | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Necklace Pride Mukhtiyar Shahadat Maindargi | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| RSM Unity Developers RSM Unity Developers | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| CENTRE COURT Maheshwari Developers | Active | 31 Jul 2028 | 31 Mar 2028 | 0 |
| Gulmohar Residency Gulmohar Residency | Active | 31 Dec 2028 | 31 Dec 2025 | 0 |
| Yarawa Residency Yarawa Buildcon LLP | Active | 31 Jul 2029 | 31 Mar 2029 | 0 |
| HEXA-VIP PRIME Hexaforce Construction LLP | Active | 31 Dec 2030 | same | 0 |
| PANJWANI MARKET V V SOMSHETTI BUILDERS LLP | Active | 30 Apr 2031 | 1 Jan 2025 | 0 |
| FLORA CASA Synergy Infra | Completed | 30 Apr 2024 | 30 Oct 2023 | 0 |
| Motiwala Skyline AYYUB USMAN MOTIWALA | Completed | 31 Dec 2025 | same | 0 |
| Skyline Residency Shree Constructions | Completed | 31 Dec 2025 | same | 0 |
| MHDCL ANTROLIKAR NAGAR SOLAPUR PMAY PROJECT MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED | Lapsed | 30 Apr 2024passed | same | 0 |
| BHAGWAN RESIDENCY RUPESH VASANT BHADULE | Lapsed | 29 Jun 2025passed | 30 Jun 2023 | 0 |
| Central Park Usman Hassam Mansuri | Lapsed | 31 Dec 2025passed | 1 Jan 2025 | 0 |
| Patel Plaza Ehsan Construction | Lapsed | 31 Dec 2025passed | same | 0 |
| Roshan Apartment Roshan Builders & Developers | Lapsed | 31 Dec 2025passed | 1 Mar 2025 | 0 |
| Sudarshan Heights Shri Mahalaxmi Builders And Developers | Lapsed | 31 Dec 2025passed | same | 0 |
| Royal Apartment Imran Mohammed Ismail Attar | Lapsed | 1 Jan 2026passed | same | 0 |
| Kalyani Majestic Farooque Ismail Kalyani | Lapsed | 30 Jun 2026passed | 1 Jul 2025 | 0 |
| Rushi Marvel Meghshyam Mallikarjun Yemul | — | — | — | 1 |
Other areas in Solapur
- Pandharpur · 38
- Solapur · 36
- Solapur · 33
- Daji Peth · 30
- Budhwar Peth · 25
- MIDC Solapur · 17
- Barshi · 11
- Majrewadi · 9
- SRPF Camp Solapur · 7
- Sangola · 5
- Solapur City · 5
- MIDC Chincholi · 3
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.