Aastha Residency
by Nitin Hukumchand Rathod · Gurunanak Nagar, Solapur
Possession date of Aastha Residency: 30 April 2027, moved from 1 June 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600028323, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Aastha Residency?
How the possession date of Aastha Residency has moved
1 June 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT52600017635)
Reason the builder gave MahaRERA:
“TO' The MahaRERA. Subject: Extension to the project bearing registration number P52600028323. Sir, I, Nitin Hukumchand Rathod, hereby apply for extension u/s 7(3) of the registered project bearing vide no PP52600028323. As prescribed under_…” Read the full reason
“TO' The MahaRERA. Subject: Extension to the project bearing registration number P52600028323. Sir, I, Nitin Hukumchand Rathod, hereby apply for extension u/s 7(3) of the registered project bearing vide no PP52600028323. As prescribed under_circular no 07/2019 dated 08 Feb 2019, the consent of 51% of the allottees is enclosed herewith.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aastha Residency’s extension records on MahaRERA (P52600028323), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aastha Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600028323
- Status
- Registered and active
- Builder
- Nitin Hukumchand Rathod
- Location
- Gurunanak Nagar, Solapur · 413003
- Project type
- Residential / Group Housing
- Registered on
- 18 Feb 2021
- Completion date at registration
- June 2025
- Latest completion date
- April 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 60
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Aastha Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aastha Residency | 100% | 68% | 43% | 5% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aastha Residency every month.
Aastha Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Aastha Residency (10 floors)
- Land: 1,456 sq m (about 0.4 acres) · sanctioned built-up 4,231 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aastha Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aastha Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aastha Residency
What is the possession date of Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aastha Residency in Gurunanak Nagar, Solapur is 30 April 2027 — 18 months later than 1 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Aastha Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aastha Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 1 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aastha Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "TO' The MahaRERA. Subject: Extension to the project bearing registration number P52600028323. Sir, I, Nitin Hukumchand Rathod, hereby apply for extension u/s 7(3) of the registered project bearing vide no PP52600028323. As prescribed under_circular no 07/2019 dated 08 Feb 2019, the consent of 51% of the allottees is enclosed herewith.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aastha Residency in Gurunanak Nagar, Solapur is P52600028323.
Is Aastha Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency is registered as P52600028323 and its status is "Registered and active".
What is the construction status of Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Aastha Residency is 68% done and internal work 43%. GharKundli's full report compares construction progress with the deadline.
Does Aastha Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aastha Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency is registered on MahaRERA as P52600028323, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Aastha Residency's possession date changes?
The latest dates are on Aastha Residency's MahaRERA page (P52600028323). GharKundli's Kundli Watch sends a free WhatsApp update on Aastha Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aastha Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency has one building filed: Aastha Residency with 10 floors.
How big is the land of Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency stands on 1,456 sq m of land (about 0.4 acres), with 4,231 sq m of sanctioned built-up area.
Where can I read reviews of Aastha Residency?
Google Maps has reviews of Aastha Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aastha Residency?
Aastha Residency by Nitin Hukumchand Rathod is in Gurunanak Nagar, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600028323, per GharKundli's check of MahaRERA records.
How many homes are in Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency has 60 homes in 1 tower registered on MahaRERA.
When was Aastha Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aastha Residency was registered on MahaRERA on 18 February 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Aastha Residency?
No court cases are listed for Aastha Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Aastha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nitin Hukumchand Rathod, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Aastha Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Solapur →
Other projects in pincode 413003
- F.F AMORA
- Kalyani Majestic
- JayPrakash Heights
- PANJWANI MARKET
- Swami Samarth Regency
- Gulmohar Residency
- Yarawa Residency
- HEXA-VIP PRIME
Other projects by Nitin Hukumchand Rathod
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.