PANJWANI MARKET

by V V SOMSHETTI BUILDERS LLP · Kasabe Solapur, Solapur

Possession date of PANJWANI MARKET: 30 April 2031, moved from 1 January 2025 (71 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52600032090, and currently active. Its completion date has moved from January 2025 to April 2031: 71 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PANJWANI MARKET?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PANJWANI MARKET has moved

  1. 1 January 2025

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EA15072502074)

    Reason the builder gave MahaRERA:
    “We, Somshetti Builders LLP, are promoter of the project Panjwani Market, registered under MahaRERA vide registration number P52600032090. Sir the foresaid project was initially sanctioned upto ground + wo upper floors (All commercial units)…” Read the full reason“We, Somshetti Builders LLP, are promoter of the project Panjwani Market, registered under MahaRERA vide registration number P52600032090. Sir the foresaid project was initially sanctioned upto ground + wo upper floors (All commercial units) and the said floors along with all the promised amenities are already constructed and part completion certificate for the mentioned floors have been received. Later, we have received a revised commencement certificate for upper third and forth floor. Construction of these floors are now commenced and shall need another five years for the completion of th…”
  3. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PANJWANI MARKET’s extension records on MahaRERA (P52600032090), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PANJWANI MARKET

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600032090
Status
Registered and active
Builder
V V SOMSHETTI BUILDERS LLP
Location
Kasabe Solapur, Solapur · 413003
Project type
Commercial
Registered on
6 Dec 2021
Completion date at registration
January 2025
Latest completion date
April 2031
Delay so far
71 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
58%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PANJWANI MARKET, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PANJWANI MARKET A Wing100%80%55%35%
PANJWANI MARKET B Wing100%80%55%35%

Commencement certificate (CC), as filed on MahaRERA

  • PANJWANI MARKET A Wing: covers 5 floors
  • PANJWANI MARKET B Wing: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PANJWANI MARKET every month.

PANJWANI MARKET: buildings, flats and land, as filed on MahaRERA

  • Buildings: PANJWANI MARKET A Wing (5 floors, 38 units) · PANJWANI MARKET B Wing (5 floors, 38 units)
  • Land: 9,941 sq m (about 2.5 acres) · sanctioned built-up 10,650 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PANJWANI MARKET →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PANJWANI MARKET: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PANJWANI MARKET

What is the possession date of PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PANJWANI MARKET in Kasabe Solapur, Solapur is 30 April 2031 — 71 months later than 1 January 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PANJWANI MARKET?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PANJWANI MARKET's builder has filed on MahaRERA, the official one, is 30 April 2031, already 71 months later than the 1 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PANJWANI MARKET extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "We, Somshetti Builders LLP, are promoter of the project Panjwani Market, registered under MahaRERA vide registration number P52600032090. Sir the foresaid project was initially sanctioned upto ground + wo upper floors (All commercial units) and the said floors along with all the promised amenities are already constructed and part completion certificate for the mentioned floors have been received. Later, we have received a revised commencement certificate for upper third and forth floor. Construction of these floors are now commenced and shall need another five years for the completion of th…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PANJWANI MARKET in Kasabe Solapur, Solapur is P52600032090.

Is PANJWANI MARKET registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET is registered as P52600032090 and its status is "Registered and active".

What is the construction status of PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 80% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does PANJWANI MARKET have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is PANJWANI MARKET safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET is registered on MahaRERA as P52600032090, its completion date has moved 71 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PANJWANI MARKET's possession date changes?

The latest dates are on PANJWANI MARKET's MahaRERA page (P52600032090). GharKundli's Kundli Watch sends a free WhatsApp update on PANJWANI MARKET every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PANJWANI MARKET have?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET has 2 buildings filed: PANJWANI MARKET A Wing with 5 floors and 38 units; PANJWANI MARKET B Wing with 5 floors and 38 units.

How big is the land of PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET stands on 9,941 sq m of land (about 2.5 acres), with 10,650 sq m of sanctioned built-up area.

Where can I read reviews of PANJWANI MARKET?

Google Maps has reviews of PANJWANI MARKET written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PANJWANI MARKET?

PANJWANI MARKET by V V SOMSHETTI BUILDERS LLP is in Kasabe Solapur, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600032090, per GharKundli's check of MahaRERA records.

How many homes are in PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET has 0 homes in 2 towers registered on MahaRERA, and 58% of them are sold or booked.

When was PANJWANI MARKET registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PANJWANI MARKET was registered on MahaRERA on 6 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on PANJWANI MARKET?

No court cases are listed for PANJWANI MARKET on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PANJWANI MARKET?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V V SOMSHETTI BUILDERS LLP.

All projects with possession due in 2031 in Solapur →

Other projects in Solapur North

All 30 projects in Gurunanak Nagar (413003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.