Deepgiri Heights
by Sachin Purushottam Kulkarni · Gurunanak Nagar, Solapur
Possession date of Deepgiri Heights: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600080850, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Deepgiri Heights?
How the possession date of Deepgiri Heights has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Deepgiri Heights’s extension records on MahaRERA (P52600080850), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Deepgiri Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600080850
- Status
- Registered and active
- Builder
- Sachin Purushottam Kulkarni
- Location
- Gurunanak Nagar, Solapur · 413003
- Project type
- Residential / Group Housing
- Registered on
- 21 Jul 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Deepgiri Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Deepgiri Heights | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Deepgiri Heights every month.
Deepgiri Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Deepgiri Heights (7 floors, 36 units)
- Car parking: 38 open
- Land: 569 sq m (about 0.1 acres) · sanctioned built-up 1,599 sq m
The builder’s record and reviews
Sachin Purushottam Kulkarni has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Deepgiri Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Deepgiri Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Deepgiri Heights
What is the possession date of Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Deepgiri Heights in Gurunanak Nagar, Solapur is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Deepgiri Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Deepgiri Heights's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Deepgiri Heights in Gurunanak Nagar, Solapur is P52600080850.
Is Deepgiri Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights is registered as P52600080850 and its status is "Registered and active".
What is the construction status of Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Deepgiri Heights is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Deepgiri Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Deepgiri Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights is registered on MahaRERA as P52600080850, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Deepgiri Heights's possession date changes?
The latest dates are on Deepgiri Heights's MahaRERA page (P52600080850). GharKundli's Kundli Watch sends a free WhatsApp update on Deepgiri Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Deepgiri Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights has one building filed: Deepgiri Heights with 7 floors and 36 units.
How much parking does Deepgiri Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 38 open car parking spaces for Deepgiri Heights.
How big is the land of Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights stands on 569 sq m of land (about 0.1 acres), with 1,599 sq m of sanctioned built-up area.
What is the track record of Deepgiri Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sachin Purushottam Kulkarni has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Deepgiri Heights?
Google Maps has reviews of Deepgiri Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Deepgiri Heights?
Deepgiri Heights by Sachin Purushottam Kulkarni is in Gurunanak Nagar, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600080850, per GharKundli's check of MahaRERA records.
How many homes are in Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights has 12 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Deepgiri Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepgiri Heights was registered on MahaRERA on 21 July 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on Deepgiri Heights?
No court cases are listed for Deepgiri Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Deepgiri Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sachin Purushottam Kulkarni, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Deepgiri Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Solapur →
Other projects in pincode 413003
- F.F AMORA
- Kalyani Majestic
- JayPrakash Heights
- PANJWANI MARKET
- Swami Samarth Regency
- Gulmohar Residency
- Yarawa Residency
- HEXA-VIP PRIME
Other projects by Sachin Purushottam Kulkarni
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.