Possession: FLORA CASA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52600007672. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about FLORA CASA?
How the possession date of FLORA CASA has moved
30 October 2023
Completion date given when the project was registered
30 April 2024
Extended at the builder's request (MahaRERA application EXT52600017876)
Reason the builder gave MahaRERA: “Due to delay in buying TDR and loading it , already we are in finishing stage and tend to complete it till March and we have not done any bookings for B building .already we have received completion certificate for A Building.”
Source: FLORA CASA’s extension records on MahaRERA (P52600007672), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on FLORA CASA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52600007672
- Status
- Completed
- Builder
- Synergy Infra
- Location
- Basaweshwar Nagar, Solapur · 413003
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- October 2023
- Latest completion date
- April 2024
- Delay so far
- 6 months
- Homes
- 105
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of FLORA CASA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| FLORA CASA | 100% | 100% | 100% | 100% |
| FLORA CASA 1 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on FLORA CASA every month.
FLORA CASA: buildings, flats and land, as filed on MahaRERA
- Buildings: FLORA CASA (10 floors) · FLORA CASA 1 (2 floors)
- Land: 3,047 sq m (about 0.8 acres) · sanctioned built-up 3,004 sq m · recreational space 444 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of FLORA CASA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
FLORA CASA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about FLORA CASA
What is the possession date of FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for FLORA CASA in Basaweshwar Nagar, Solapur is 30 April 2024 — 6 months later than 30 October 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for FLORA CASA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date FLORA CASA's builder has filed on MahaRERA, the official one, is 30 April 2024, already 6 months later than the 30 October 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of FLORA CASA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA's builder applied to MahaRERA to extend the completion date once: to 30 April 2024, giving the reason "Due to delay in buying TDR and loading it , already we are in finishing stage and tend to complete it till March and we have not done any bookings for B building .already we have received completion certificate for A Building.".
What is the RERA number of FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of FLORA CASA in Basaweshwar Nagar, Solapur is P52600007672.
Is FLORA CASA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA is registered as P52600007672 and its status is "Completed".
What is the construction status of FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does FLORA CASA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is FLORA CASA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA is registered on MahaRERA as P52600007672, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if FLORA CASA's possession date changes?
The latest dates are on FLORA CASA's MahaRERA page (P52600007672). GharKundli's Kundli Watch sends a free WhatsApp update on FLORA CASA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does FLORA CASA have?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA has 2 buildings filed: FLORA CASA with 10 floors; FLORA CASA 1 with 2 floors.
How big is the land of FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA stands on 3,047 sq m of land (about 0.8 acres), with 3,004 sq m of sanctioned built-up area and 444 sq m of recreational open space.
Where can I read reviews of FLORA CASA?
Google Maps has reviews of FLORA CASA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is FLORA CASA?
FLORA CASA by Synergy Infra is in Basaweshwar Nagar, Solapur (pincode 413003), Maharashtra, and is registered on MahaRERA as P52600007672, per GharKundli's check of MahaRERA records.
How many homes are in FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA has 105 homes in 2 towers registered on MahaRERA.
When was FLORA CASA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), FLORA CASA was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on FLORA CASA?
No court cases are listed for FLORA CASA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of FLORA CASA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Synergy Infra.
Check it yourself on MahaRERA
- How to check the possession date of FLORA CASA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Solapur North
- Kaizen Emerald
- SAMARTH PRASAD
- VIJAYS THE PRESTIGE
- Shivtej Plaza
- PRAJAY HEIGHTS
- F.F AMORA
- Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman Sanstha
- SHHRADDHA AVENUE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.