Possession date of Pinnacle 33 Avenue: 1 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52600052490. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Pinnacle 33 Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Pinnacle 33 Avenue has moved

  1. 1 June 2026

    Completion date given when the project was registered

  2. 1 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Pinnacle 33 Avenue’s extension records on MahaRERA (P52600052490), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Pinnacle 33 Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600052490
Status
Lapsed (registration period ended)
Builder
Ranjeet Kantilal Shah
Location
Murarji Peth, Solapur · 413001
Project type
Residential / Group Housing
Registered on
8 Sep 2023
Completion date at registration
June 2026
Latest completion date
October 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
26
Sold or booked
32%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Pinnacle 33 Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Pinnacle 33 Avenue98%90%45%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pinnacle 33 Avenue every month.

Pinnacle 33 Avenue: buildings, flats and land, as filed on MahaRERA

  • Buildings: Pinnacle 33 Avenue (8 floors)
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 3,323 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Pinnacle 33 Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Pinnacle 33 Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Pinnacle 33 Avenue

What is the possession date of Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Pinnacle 33 Avenue in Murarji Peth, Solapur is 1 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Pinnacle 33 Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Pinnacle 33 Avenue's builder has filed on MahaRERA, the official one, is 1 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Pinnacle 33 Avenue in Murarji Peth, Solapur is P52600052490.

Is Pinnacle 33 Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue is registered as P52600052490 and its status is "Lapsed (registration period ended)".

What is the construction status of Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Pinnacle 33 Avenue is 90% done and internal work 45%. GharKundli's full report compares construction progress with the deadline.

Does Pinnacle 33 Avenue have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Pinnacle 33 Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue is registered on MahaRERA as P52600052490, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Pinnacle 33 Avenue's possession date changes?

The latest dates are on Pinnacle 33 Avenue's MahaRERA page (P52600052490). GharKundli's Kundli Watch sends a free WhatsApp update on Pinnacle 33 Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Pinnacle 33 Avenue have?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue has one building filed: Pinnacle 33 Avenue with 8 floors.

How big is the land of Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue stands on 1,000 sq m of land (about 0.2 acres), with 3,323 sq m of sanctioned built-up area.

Where can I read reviews of Pinnacle 33 Avenue?

Google Maps has reviews of Pinnacle 33 Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Pinnacle 33 Avenue?

Pinnacle 33 Avenue by Ranjeet Kantilal Shah is in Murarji Peth, Solapur (pincode 413001), Maharashtra, and is registered on MahaRERA as P52600052490, per GharKundli's check of MahaRERA records.

How many homes are in Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue has 26 homes in 1 tower registered on MahaRERA, and 32% of them are sold or booked.

When was Pinnacle 33 Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Pinnacle 33 Avenue was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Pinnacle 33 Avenue?

No court cases are listed for Pinnacle 33 Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Pinnacle 33 Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ranjeet Kantilal Shah.

All projects with possession due in 2026 in Solapur →

Other projects in Solapur North

All 33 projects in Solapur (413001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.